1.

What is the primary obligation of the employer in a construction contract?

a)

Supervising the contractor's work

b)

Making timely payment to the contractor

c)

Certifying materials on site

d)

Preparing the final account

2.

According to Clause 30.1, what happens if a contractor fails to submit a payment application?

a)

The architect must still issue a certificate

b)

The contractor waives his entitlement to payment for that period

c)

The QS can certify payment on his behalf

d)

The employer becomes liable for breach of contract

3.

Who is responsible for issuing the Interim Certificate?

a)

Contractor

b)

Quantity Surveyor

c)

Architect

d)

Employer

4.

Within how many days must the architect issue the Interim Certificate after receiving a valid payment application?

a)

14 days

b)

21 days

c)

30 days

d)

7 days

5.

What is the role of the Quantity Surveyor under Clause 30.1?

a)

Sign the final account

b)

Issue interim certificates

c)

Value the contractor's application

d)

Represent the contractor

6.

Under Clause 30.2, which of the following is NOT included in the amount due in an Interim Certificate?

a)

Total value of work executed

b)

Estimated future work

c)

Value of stored materials

d)

Less retention and previously certified sums

7.

Which of the following is a condition for including materials in an Interim Certificate?

a)

Materials must be adjacent to the site

b)

Materials must be properly stored and secured

c)

Materials must be intended for temporary works

d)

Materials must be paid by subcontractors

8.

What happens if the employer fails to honor the Interim Certificate without reasonable cause?

a)

It is considered best practice

b)

It is referred to the contractor’s lawyer

c)

It is considered a breach of contract

d)

The architect must revise the certificate

9.

What type of payment scheme is NOT typical under PAM contracts?

a)

Stage-based payment

b)

Monthly interim payment

c)

Daily cash advances

d)

Payment after final certificate

10.

After the Certificate of Practical Completion, what must happen for further payments to be made?

a)

The contractor stops submitting applications

b)

The architect and QS must ascertain payable amounts

c)

The employer determines the payment

d)

No payments are allowed after completion

11.

What is implied if the contractor does not comply with the required content in a payment application?

a)

The contractor can appeal to the court directly

b)

The architect must approve the claim regardless

c)

The QS and architect may reject or undervalue the claim

d)

The employer must pay as per the claim

12.

What is the legal effect of an architect issuing an Interim Certificate?

a)

It confirms the contractor’s employment

b)

It obliges the employer to make payment within the honoring period

c)

It automatically extends the project timeline

d)

It releases the performance bond

13.

Which document defines the timing of interim claim intervals under Clause 30.1?

a)

The project manual

b)

The site diary

c)

The appendix to the conditions of contract

d)

The QS’s monthly report

14.

What is the architect’s duty if they receive an appeal on undervaluation from the contractor?

a)

Reassess the valuation report

b)

Ignore the appeal

c)

Refer the matter to the court

d)

Cancel the interim certificate

15.

What is considered good practice when serving certificates?

a)

Only giving it to the employer

b)

Publishing it on site

c)

Not issuing any certificate until project completion

d)

Issuing copies to both the contractor and nominated subcontractors