SBEQ2523 Variation

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

What does the term 'variation' commonly refer to in construction contracts?

a)

A breach of contract

b)

A change to the originally agreed works

c)

A penalty for delay

d)

A new contract agreement

2.

Which of the following is NOT typically a reason for a variation?

a)

Changes in employer requirements

b)

Review of design

c)

Payment delays

d)

Statutory changes

3.

According to PAM 2018, which clause defines variation?

a)

Clause 11.0

b)

Clause 24.0

c)

Clause 1.1

d)

Clause 10.3

4.

Who is typically empowered to issue a variation under PAM 2018?

a)

Contractor

b)

Employer

c)

Architect

d)

Quantity Surveyor

5.

Which clause ensures that variations do not vitiate the contract?

a)

Clause 11.1

b)

Clause 11.2

c)

Clause 11.4

d)

Clause 24.3

6.

What must accompany the notification of a variation claim under Clause 11.7(a)?

a)

Site photographs

b)

Verbal approval

c)

Preliminary estimate and calculations

d)

Copy of contract

7.

What is the deadline for submitting a notice of additional expense due to variation?

a)

14 days

b)

21 days

c)

28 days

d)

60 days

8.

Who is primarily responsible for valuing variations?

a)

Architect

b)

Employer

c)

Contract Administrator

d)

Quantity Surveyor

9.

Which of the following is considered an invalid variation?

a)

Changes to material type

b)

Genuine omission of work

c)

Omission to award work to another contractor

d)

Substitution of work item

10.

What type of work does Clause 11.1(a) include?

a)

Installation of services

b)

Additional overhead

c)

Addition, omission, or substitution of work

d)

Site handover

11.

What must a contractor do upon receiving a valid AI for variation?

a)

Wait for payment confirmation

b)

Request an extension of time

c)

Comply and carry out the work

d)

Submit a counterproposal

12.

Which of the following is excluded from the definition of variation under Clause 11.1?

a)

Substitution of materials

b)

Changes to working space

c)

Rectification of contractor’s negligence

d)

Removal of work from site

13.

In what situation may a verbal instruction be considered valid for a variation?

a)

If the contractor agrees

b)

In emergencies, with later written confirmation

c)

If the employer signs it

d)

Only in design-build contracts

14.

Which stage follows the identification of the need for varied work?

a)

Contract administrator’s recommendation

b)

Site inspection

c)

Identification of work particulars

d)

Legal consultation

15.

What is the purpose of maintaining a variation order register?

a)

To track subcontractor payments

b)

To ensure clear documentation of variations

c)

To estimate taxes

d)

To verify tender documents