ตาม ITP Quality Intervention points : H ย่อมาจากอะไร
Witness Point
Spot Witness Point
Hold Point
Inform Point
โครงการนี้ ITR ที่ใช้ในการเขียน Punch List คือข้อใด
ITR-W-0115X-S
ITR-W-0116X-S
ITR-W-0117X-S
ITR-W-0120A-S
Punch Description ของ Punch “A” คือข้อใด
Shall be cleared prior to Pre-Commissioning
Shall be cleared prior to the reinstatement
Shall be cleared prior to the hydrotest
Shall be cleared prior to the commissioning
ข้อใดต่อไปนี้ไม่อยู่ในกลุ่ม Punch Category “A”
RLM Isometrics and PEFS to be attached in all test packs
Secondary welded support not yet installed
Out of plumbness, levelness, mis-alignment
Check the slope if required by isometric drawings.
ข้อใดต่อไปนี้ไม่อยู่ในกลุ่ม Punch Category “B”
Temporary supports for the hydrotest shall be removed
Secondary welded support not yet installed
Out of plumbness, levelness, mis-alignment
Spectacle blind and spacer to be installed after test
อุปกรณ์ใดต่อไปนี้ไม่เกี่ยวข้องกับงาน Line check
Welding gauge
ตลับเมตร
Infrared thermometer
ระดับน้ำ
ใน Isometrics ระบุ Slop 1 : 200 mm. ถ้าความยาวท่อที่ 1500 mm. จะมีค่า Slop เท่ากับกี่ mm.
6 mm.
6.5 mm.
7 mm.
7.5 mm.
เอกสารอะไรไม่เกี่ยวข้องกับงาน Line check
Standard pipe support
Painting report
P&ID
Isometrics
“Out of plumbness, levelness, mis-alignment” จัดอยู่ในกลุ่ม Punch Category ใด
Punch Category “A”
Punch Category “B”
Punch Category “C”
Punch Category “B, C”
“Secondary welded support not yet installed” จัดอยู่ในกลุ่ม Punch Category ใด
Punch Category “A”
Punch Category “B”
Punch Category “C”