PRE-TEST INSPECTION TEST REPORT ELECTRICAL INSTRUMENT

Total questions: 20

Worksheet time: 2mins

Name
Class
Date
1.
Apa yang dimaksud dengan ITR/A?
a)
ITR Classification A in Precommissioning Phase
b)
ITR Classification B in Precommissioning Phase
c)
ITR Classification A in Construction Phase
d)
ITR Classification B in Construction Phase
2.

Nomer ITR yang digunakan dalam inspeksi pengetesan kabel Instrument yaitu

a)

ITR-CI-00014-13

b)

ITR-EL-00037-06

3.
Punchlist yang timbul dari adanya temuan pada saat inspeksi Electrical fasa construction adalah
a)
P-CON-IC-XXXX
b)
P-CON-EL-XXXX
c)
P-PRE-EL-XXXX
d)
P-LIC-EL-XXXX
4.
Apa yang termasuk dalam pemeriksaan Bending radius pada checksheet ITR ini
a)
Memastikan radius lengkungan kabel sesuai standar untuk menghindari kerusakan
b)
Mengecek warna kabel
c)

Memverifikasi panjang kabel sesuai cable schedule

d)

Memverifikasi tipe kabel sesuai cable schedule

5.
Apa yang termasuk dalam pemeriksaan "Check bonding and grounding connection if any"?
a)
Mengecek warna kabel
b)
Memverifikasi panjang tubing
c)
Memastikan koneksi bonding dan grounding terpasang dengan benar (jika ada)
d)
Memeriksa tekanan udara
6.
Mengapa pemeriksaan "Earth connections of LCS/JB/Supports are provided" sangat kritis?
a)
Untuk memastikan estetika instalasi
b)

Mencegah electric shock, static discharge, dan memenuhi kaidah lightning protection

c)
Hanya diperlukan untuk peralatan bertegangan tinggi
d)

Agar LCS/JB/Supports dapat berfungsi

7.
Apa tujuan utama dari pemeriksaan "Correct cable gland/MCT used, and assembly checked" dalam ITR ini?
a)
Memastikan warna kabel sesuai dengan standar
b)
Memverifikasi penggunaan gland/MCT yang tepat dan pemasangannya benar
c)
Mengecek panjang kabel yang digunakan
d)

Memastikan gland/MCT terpasang

8.

ITR pada gambar apakah applicable dalam pemasangan Instrument Type Valve? (Berdasarkan ITP Instrument Works)

a)
Ya
b)
Tidak
9.
Apa tujuan spesifik dari pemeriksaan "Check FDN, welding, bolting and level for stanchion"?
a)
Memastikan estetika instalasi
b)
Mengecek warna cat stanchion
c)
Memverifikasi material yang digunakan
d)
Verifikasi kekuatan struktur penyangga instrument
10.
ITR pada gambar ini digunakan untuk Inspeksi agenda apa?
a)

Motor Solo Run

b)

LV Cable Test

c)
Cable Laying
d)
High Potential Test (Hipot)
11.
Apa yang dimaksud dengan ITR/B Class Loop Test?
a)
ITR Classification A in Precommissioning Phase for Loop Test Activity
b)
ITR Classification B in Construction Phase for Loop Test Activity
c)
ITR Classification A in Commissioning Phase for Loop Test Activity
d)
ITR Classification B in Precommissioning Phase for Loop Test Activity
12.
Apa yang dimaksud dengan ITR/B Class Site Acceptance Test (SAT)?
a)
ITR Classification A in Precommissioning Phase for SAT Activity
b)
ITR Classification B in Precommissioning Phase for SAT Activity
c)
ITR Classification B in Comissioning Phase for SAT Activity
d)
ITR Classification A in Comissioning Phase for SAT Activity
13.
Apa yang dimaksud dengan ITR/B Class Motor Solo Run?
a)
ITR Classification A in Precommissioning Phase for Motor Solo Run Activity
b)
ITR Classification B in Comissioning Phase for Motor Solo Run Activity
c)
ITR Classification B in Precommissioning Phase for Motor Solo Run Activity
d)
ITR Classification A in Comissioning Phase for Motor Solo Run Activity
14.
Apa tujuan pengukuran suhu pada bagian "DE" dan "NDE" dalam tabel "Testing Condition"?
a)

Mengukur panas pada shaft motor

b)
Memantau panas pada bantalan (bearing) motor
c)
Mengukur kecepatan putaran motor
d)

Mengukur panas pada winding motor

15.
Berapakah alarm Low - Low pada index ini?
a)
2,2
b)
1,2
c)
1,7
d)
Tidak Ada
16.
Pada pengisian kolom "Control System", jika instrumen digunakan dalam sistem pemadam otomatis berbasis gas, maka centang yang tepat adalah:
a)
SIS
b)
FGS
c)
BPCS
d)
PLC
17.
Jika "Inspection result" diisi "As noted", apa artinya?
a)
Pengujian gagal total
b)

Ada catatan yang perlu didokumentasikan yang tidak ada dalam checksheet

c)

Hasil Inspeksi sudah sesuai checksheet

d)
Tidak ada data yang dicatat
18.
Apa yang Inspector lakukan apabila ITR pada saat Loop Test tidak sesuai dengan jenis Instrument yang sedang diinspeksi? (Agenda Loop Test Transmitter tetapi yang dibawa ITR untuk Control Valve)
a)
Reject agenda Loop Test dikarenakan form ITR tidak sesuai
b)
Loop Test tetap lanjut tetapi Inspector tidak tanda tangan sampai form diperbaiki
c)
Postpone sampai ITR diperbaiki oleh subkontraktor
d)
Standby di kantor
19.

Apa yang harus diperiksa dalam "Cable Insulation Resistance Test"?

a)

Nilai resistansi kabel

b)

Nilai resistansi konduktor

c)

Nilai resistansi isolasi kabel

d)

Nilai resistansi armor

20.

Berikut yang bukan tujuan untuk memverifikasi "Grounding System" dalam ITR adalah

a)

Menghindari risiko kebakaran dan kejutan listrik

b)

Menghindari resiko tersengat listrik

c)

Mencegah kerusakan pada peralatan

d)

Hanya diperlukan untuk peralatan bertegangan rendah