wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Midterm Exam: Project Management

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

In a project managed using a stage-gate approach, who decides if the project moves to the next stage or gets terminated?

a)

Project sponsor

b)

Key master

c)

Gatekeeper

d)

Subject matter expert

2.

Who is ultimately responsible to make sure that all work required by the SOW and only the work required by the SOW is performed?

a)

Project manager

b)

Customer

c)

Appropriate subject matter expert for that work package

d)

Project sponsor

3.

Usually, the three main performance criteria are time, scope and _______?

a)

Profit

b)

Cost

c)

Compliance

d)

Risks

4.

Which of the following is an estimating pitfall?

a)

Failure to use correct estimating techniques.

b)

Misinterpretation of the Statement of Work (SOW)

c)

Inaccurate Work Breakdown Structure (WBS)

d)

All of the above

5.

Given that an activity has an early start of week 12, an early finish of week 15, a late start of week 16 and a late finish of week 19, what is the slack?

a)

3 weeks

b)

4 weeks

c)

5 weeks

d)

No slack

6.

Which of the following scheduling tools is NOT based on a network approach?

a)

Program Evaluation & Review Technique

b)

Graphical Evaluation & Review Technique

c)

Critical Path Method

d)

Line of balance

7.

Which of the following is false concerning the critical path in a network?

a)

It is the path that takes the longest in the network

b)

It is the path that contains the greatest number of activities

c)

It is the shortest amount of time in which the project can be completed

d)

It is the path where each activity has zero slack

8.

______ is usually not considered a direct cost.

a)

Labor

b)

Office rent

c)

Material

d)

Parts

9.

Which of the following cannot be determined after performing a forward pass and a backward pass on a network diagram?

a)

The efforts involved for each activity

b)

The critical path

c)

The slack in each activity

d)

The end date of the project

10.

Bidder conferences are used to:

a)

Answer questions about the project prior to submittal of proposals

b)

Answer questions about the project after contract award

c)

Debrief the bidder on their performance after completion of the contract

d)

Solicit pricing information from the bidders on proposed scope changes

11.

Scope creep is often the result of:

a)

Too much detail in the specifications

b)

Poorly defined SOW

c)

Having the wrong people assigned to the project

d)

Having too many levels in the WBS

12.

Learning curve theory is based upon:

a)

The amount of improvement increases as more units are produced

b)

The time required to perform a task increases as the task is repeated

c)

The rate of improvement has sufficient consistency to allow its use as a predictive tool

d)

All of the above

13.

In order to get the most skilled workers to be assigned to their project, a project manager should use a win-lose approach when negotiating with the functional managers.

a)

True

b)

False

14.

If a worker is paid $50 per hour and the project has an overhead rate of 50%, at what rate will the work be reflected in the budget?

a)

$25 per hour

b)

$50 per hour

c)

$75 per hour

d)

$100 per hour

15.

During contract negotiations, the goal of the buyer is to:

a)

Get the seller to accept the greatest risk

b)

Get the seller to agree to scope changes at no cost to the buyer

c)

Try to get the least amount of work done at the lowest price

d)

Get the highest quality result for the lowest price