1.

From the given Activity on Arrow AOA network, what is/are the precedence of Activity C?

a)

B only

b)

A and B

c)

A, B and D

d)

B and D

2.

In the given AOA network, the precedence activity(ies) of Activity H is/are?

a)

G only

b)

C and G

c)

B and G

d)

B, D and G

3.

In the given Activity on Node AON network, the precedence of Activity F is/are?

a)

C only

b)

D only

c)

A and C

d)

C and D

4.

The CRITICAL PATH of the network is the _________.

a)

longest path

b)

path where activities cannot be delayed

c)

duration of the project

d)

ALL OF THESE