WorksheetsPlumbing pressure test Pipework Quiz
Total questions: 15
Worksheet time: 8mins
What is the test pressure for hot and cold water systems according to BSEN806 pt 4?
MDP x 1.5
MOP x 1.2
MOP x 1.5
MDP x 1.1
What does MDP stand for?
Maximum Design Pressure
Minimum Design Pressure
Maximum Durable Pressure
Minimum Durable Pressure
What is the test pressure for a system with a MOP of 2 bar?
2.5 bar
3.3 bar
3.0 bar
2.0 bar
Which test procedure is used for linear elastic materials?
Test D
Test C
Test B
Test A
How long should the test pressure be applied in Test A?
30 minutes
20 minutes
10 minutes
40 minutes
What should be done if there is a pressure loss during Test A?
Stop the test immediately
Increase the pressure
Decrease the pressure
Maintain the test pressure until all leaks are found
How long should the pressure remain constant after reduction in Test B?
30 minutes
10 minutes
20 minutes
40 minutes
What indicates a leak in Test C after 120 minutes?
Pressure drops more than 0.2 bar
Pressure increases by 0.2 bar
Pressure drops less than 0.2 bar
Pressure remains constant
What is the test pressure for visco-elastic materials with DN/OD ≤ 63mm?
Test procedure B or C
Test procedure A
Test procedure D
Test procedure E
What is the MDP for a system with a MOP of 2 bar?
4 bar
3.5 bar
2.5 bar
3 bar
What is the test pressure for a system with a MOP of 2 bar according to BSEN806 pt 4?
2.5 bar
2.8 bar
3.3 bar
3.0 bar
What should be done if there is a further pressure drop after reduction in Test B?
Stop the test
Ignore the drop
Increase the pressure
Identify the leak
What is the pressure drop limit in Test C after 30 minutes?
0.4 bar
0.2 bar
0.6 bar
0.8 bar
What is the purpose of venting all air to atmosphere before testing?
To stop leaks
To decrease pressure
To increase pressure
To ensure accurate pressure readings
What is the test pressure for combined systems with DN/OD ≤ 63mm?
Test procedure D
Test procedure E
Test procedure B or C
Test procedure A