interactive Quiz WTE

Total questions: 10

Worksheet time: 10mins

Name
Class
Date
1.

1. Which of the following factors generally lead to an increase in population?

a)

High death rate and low birth rate

b)

Industrial growth, better living conditions, and urban development

c)

Poor sanitation and limited water supply

d)

Lack of job opportunities and migration

2.

2. The Arithmetic Method is most suitable for:

a)

A) Small towns with rapid expansion

b)

B) Newly developed industrial areas

c)

C) Large and old cities

d)

D) Rural areas with unstable growth

3.

3. The Geometric Increase Method is also known as:

a)

Uniform Percentage Method

b)

Declining Method

c)

Saturation Curve Method

d)

Linear Growth Method

4.

4. The Declining Growth Method is used when:

a)

The city is growing very fast

b)

The rate of population increase is constant

c)

The rate of growth is decreasing as the city nears saturation

d)

The city has no previous census data

5.

The Logistic Curve Method is characterized by:

a)

A straight-line population increase

b)

An S-shaped curve showing growth up to saturation

c)

A rapidly declining trend

d)

Irregular fluctuations in population

6.

6. “Unaccounted-for” water losses are mainly due to:

a)

A) Population growth

b)

Meter reading errors, leaks, and unauthorized connections

c)

Increased industrial production

d)

Natural evaporation

7.

7. The Maximum Month Water Demand (MMD) typically equals:

a)

1.1 to 1.2 qₐᵥ

b)

1.5 to 1.8 qₐᵥ

c)

2.0 to 2.5 qₐᵥ

d)

1.25 to 1.5 qₐᵥ

8.

8. One important location criterion for intake is:

a)

It should be in the purest part of the source and upstream of the city

b)

It should be downstream from the wastewater discharge point

c)

It should be near polluted zones for easy access

d)

It should be on a curve of the river for strong flow

9.

9. A Pipe Intake is most suitable when:

a)

Stream is narrow and shallow

b)

Stream is wide, deep, and has high fluctuation in water level

c)

Shore pollution is low

d)

The bottom is sandy

10.

10. When designing a water treatment plant, it should be based on:

a)

Maximum day water demand (MDD)

b)

Minimum monthly water demand

c)

Average daily water demand (ADD) only

d)

Peak hourly demand