8. Earthing & Bonding, Clearances, Safety and Quality Procedures

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

Size of the MS flat used in DFCC TSS is

a)

40 x 6 mm

b)

50 x 6 mm

c)

100 x 8 mm

d)

75 x 8 mm

2.

Identify the type of bond shown.

a)

None of these

b)

Rail bond

c)

Impedance bond

d)

Structure bond

3.

Long time clearance is

a)

200 mm

b)

250 cm

c)

250 mm

d)

200 cm

4.

The distance between the two earthing rods should not be more than

a)

1 km

b)

0.5 km

c)

2 km

d)

1.5 km

5.

BEC conductors should be connected to the track every

a)

450 m

b)

200 m

c)

350 m

d)

100 m

6.

AEC conductor is provided on the super mast.

a)

False

b)

True

7.

Individual Earth Value of an Earthing station should not be more than 10 Ohms.

a)

False

b)

True

8.

During a traffic block, which type of vehicle movement is restricted in block section?

a)

Electric hauled

b)

Diesel hauled

c)

Steam hauled

d)

All the above

9.

Who is nominated to obtain the OHE power block from the CTPC?

a)

Site Engineer

b)

Authorized Person

c)

Site in charge

d)

Package Manager

10.

Before running passenger trains, the section will be inspected by

a)

CRS

b)

PMC

c)

Sr. DEE

d)

CEO

11.

Final checking of OHE should be done by the Tower Car.

a)

True

b)

False

12.

Discharge rods are to be provided while working under a power block.

a)

True

b)

False

13.

The FRP Insulator Cover is provided for

a)

Reducing weight

b)

Insulation and safety from electric contact

c)

Thermal expansion

d)

Alignment

14.

Which safety feature is included in RRCS operation?

a)

Voltage detection interlock

b)

Manual switch operation

c)

Separate supply feeder

d)

Counterweight tensioner

15.

Which device is used in the 3rd Rail system for discharging during maintenance?

a)

Ramp

b)

Insulator

c)

Short-Circuiting Device

d)

Cover Fastener