According to the material, what is the primary difference between hazard identification and risk assessment?
Hazard identification estimates the magnitude of risk, while risk assessment recognizes whether a hazard exists
Hazard identification recognizes and characterizes the existence of a hazard, while risk assessment estimates the magnitude and decides if the risk is tolerable
Hazard identification sets safe work practices, while risk assessment provides PPE requirements
Hazard identification measures exposure levels, while risk assessment lists hazard sources
Which statement best explains why organisations carry out risk assessment?
It is primarily a public relations requirement to improve company image
It provides a more effective way of managing hazards and meets legal and management system requirements
It replaces the need for supervision and worker consultation
It is only required for emergency situations and not routine work
Under a valid permit, only approved people are permitted to carry out work. Which combination best captures the constraints specified?
Any job, at any time, at any place
A specific job, at a specific time, at a specific place
Multiple jobs, at flexible times, across multiple sites
Emergency tasks only, at night, within restricted zones
Which item is one of the four important protections of the Permit To Work system?
Shareholder dividends
Personnel’s safety
Only production output
Marketing reputation metrics unrelated to safety
Beyond people and environment, the PTW system also protects which two categories?
Product quality and advertising spend
Asset—facilities or equipment for producing oil and gas, and the reputation of the company
Supplier contracts and tax liabilities
Only office furniture and IT systems
Refer to the illustrated Permit To Work (PTW) form. Which section is specifically indicated to be completed by the contractor before work begins?
Bhg. B: Diisi Oleh PTJ (Penyelia Projek)
Bhg. A: Diisi Oleh Kontraktor
Penerangan Kerja
Keperluan Kelengkapan Perlindungan Diri
Based on the PTW example, what is stated as mandatory before work is carried out by PTJ?
Completion of Waktu kerja tambahan
Approval of Penerangan Kerja by contractor
Wajib dipatuhi oleh kontraktor sebelum kerja dilaksanakan
Keperluan Kelengkapan Perlindungan Diri WAJIB (Mandatory)
In the Lifting Plan form, what instruction is printed at the top regarding timing of completion?
Complete this Lifting Plan after the job is finished
Complete this Lifting Plan before starting the job
Complete this Lifting Plan when equipment is ordered
Complete this Lifting Plan only if a tower crane is used
Which information appears in SECTION 1: CRANE DETAILS of the Lifting Plan?
Location of lift and planned lift date
Type of crane, brand name, and model
Rigging weights and total lifting weight
Operator signature and date
Which parameter in the Lifting Plan relates to geometry of the lift and directly affects chart capacity?
Number of parts of line
Radius
Planned lift date
Operator’s brand name