Module MT207 Exam: Planning and Scheduling

Total questions: 25

Worksheet time: 13mins

Name
Class
Date
1.

A tool supervisors use to foresee changes and make adjustments to ensure the project stays on track is a _____.

a)

diagram

b)

inventory

c)

flowchart

d)

schedule

2.

The steps a supervisor takes when planning labor include all of the following except _____.

a)

completing an equipment estimate first

b)

identifying the skills required for the job

c)

determining how many workers are needed

d)

deciding which workers will make up the crew

3.

The span of responsibility for a contractor starts from obtaining the contract and ends with _____.

a)

ensuring all safety inspections are completed

b)

scheduling the final meeting with the architect

c)

transferring ownership of the project to the client

d)

receiving completed work reports from all subcontractors

4.

Crew leaders use a _____ to construct a more efficient and effective way to plan a job.

a)

task objective

b)

job analysis

c)

job-site log

d)

project estimate

5.

A _____ is a diagram used to identify each phase of a project, its deliverables, and the tasks required for each deliverable.

a)

work breakdown structure

b)

work coordination schedule

c)

structured hierarchy of work

d)

schedule of work performed

6.

Using the formula: materials quantity divided by the production rate, multiplied by the modifier helps a supervisor _____.

a)

coordinate the timing of all materials delivered

b)

assign the correct number of crew members to the job

c)

determine the time required to complete a job

d)

divide all materials among each crew on site

7.

A short-term schedule is a control technique that extracts a detailed production schedule for projects that are less than _____ months duration.

a)

twelve

b)

nine

c)

six

d)

three

8.

If a job is to be built on schedule and within budget, the supervisor must learn the methods of developing, reviewing, and _____ a job plan.

a)

leveraging

b)

advancing

c)

selecting

d)

discarding

9.

The major disadvantage of a _____ is that it requires training to be used effectively and, consequently, is not understood or accepted by many field supervisors.

a)

network diagram

b)

safety briefing

c)

document log

d)

bar charts

10.

Planners completing a work breakdown use a combination of all of the following factors to guide them in deciding the level of detail needed except _____.

a)

previous experience

b)

building regulations

c)

company policies

d)

supervisor input

11.

Before materials arrive at a job site, the supervisor must develop a plan to handle the materials that includes all of the following except _____.

a)

time to unload

b)

inspecting and testing

c)

submitting purchase orders

d)

retrieval from storage

12.

Once tasks are delegated to the crew, a supervisor _____ on a job site to anticipate scheduling conflicts and ensure the work assigned is performed.

a)

requires time sheets

b)

implements a quality control system

c)

follows up frequently

d)

monitors safety records

13.

Identifying what work activities are required to achieve a goal is part of the _____ process.

a)

document

b)

planning

c)

submittal

d)

transmittal

14.

Developing a schedule on paper helps a supervisor mentally build a project, attempting to _____ that may occur later.

a)

limit material defects

b)

prevent safety breaches

c)

decrease absenteeism

d)

avoid planning errors

15.

“At 3:00 p.m. tomorrow, all plumbing will be installed” is an example of an _____.

a)

objective

b)

allotment

c)

undertaking

d)

assignment

16.

Planners use _____ to determine what labor, equipment, and other means are required for an upcoming project.

a)

stored assets

b)

resource profile

c)

quality control

d)

finished projects

17.

The concept of precedence that is fundamental to a network diagram states that _____.

a)

Activity B is optional according to the budget

b)

Activity B cannot begin until Activity A is complete

c)

Activity A is a higher priority than Activity B

d)

Activity A is scheduled before Activity B

18.

A _____ provides a supervisor with information to direct work efforts efficiently and use resources to their full potential.

a)

bid

b)

log

c)

plan

d)

task

19.

On a schedule, a light line that extends past an activity’s duration represents a(n) _____.

a)

activity float

b)

delayed activity

c)

added activity

d)

completed activity

20.

The time to complete specific activities can reasonably be estimated by various experts including all of the following except _____.

a)

personal experience

b)

equipment manufacturers

c)

subcontractors

d)

OSHA inspectors

21.

Showing how all activities relate to each other is a(n) _____.

a)

major advantage of network diagrams

b)

interviewing skill used by recruiters

c)

technique used to demonstrate logic

d)

part of developing document control

22.

Negotiating a price for the job is part of the _____ stage of planning.

a)

construction

b)

implementation

c)

follow-up

d)

pre-construction

23.

Checking tools in and out through the supervisor has many advantages, including the following, except _____.

a)

producing effective control

b)

reducing wasted time

c)

eliminating worker injuries

d)

maintaining the repair schedule

24.

Supervisors should avoid _____ when conducting job-site meetings.

a)

beginning the meeting late

b)

stating the meeting’s purpose

c)

providing time for questions

d)

repeating items for clarity

25.

Benefits of a bar chart include all of the following except _____.

a)

recording job progress

b)

setting vacation schedules

c)

displaying built-in slack time

d)

helping to create resource profiles