WorksheetsModule MT207 Exam: Planning and Scheduling
Total questions: 25
Worksheet time: 13mins
A tool supervisors use to foresee changes and make adjustments to ensure the project stays on track is a _____.
diagram
inventory
flowchart
schedule
The steps a supervisor takes when planning labor include all of the following except _____.
completing an equipment estimate first
identifying the skills required for the job
determining how many workers are needed
deciding which workers will make up the crew
The span of responsibility for a contractor starts from obtaining the contract and ends with _____.
ensuring all safety inspections are completed
scheduling the final meeting with the architect
transferring ownership of the project to the client
receiving completed work reports from all subcontractors
Crew leaders use a _____ to construct a more efficient and effective way to plan a job.
task objective
job analysis
job-site log
project estimate
A _____ is a diagram used to identify each phase of a project, its deliverables, and the tasks required for each deliverable.
work breakdown structure
work coordination schedule
structured hierarchy of work
schedule of work performed
Using the formula: materials quantity divided by the production rate, multiplied by the modifier helps a supervisor _____.
coordinate the timing of all materials delivered
assign the correct number of crew members to the job
determine the time required to complete a job
divide all materials among each crew on site
A short-term schedule is a control technique that extracts a detailed production schedule for projects that are less than _____ months duration.
twelve
nine
six
three
If a job is to be built on schedule and within budget, the supervisor must learn the methods of developing, reviewing, and _____ a job plan.
leveraging
advancing
selecting
discarding
The major disadvantage of a _____ is that it requires training to be used effectively and, consequently, is not understood or accepted by many field supervisors.
network diagram
safety briefing
document log
bar charts
Planners completing a work breakdown use a combination of all of the following factors to guide them in deciding the level of detail needed except _____.
previous experience
building regulations
company policies
supervisor input
Before materials arrive at a job site, the supervisor must develop a plan to handle the materials that includes all of the following except _____.
time to unload
inspecting and testing
submitting purchase orders
retrieval from storage
Once tasks are delegated to the crew, a supervisor _____ on a job site to anticipate scheduling conflicts and ensure the work assigned is performed.
requires time sheets
implements a quality control system
follows up frequently
monitors safety records
Identifying what work activities are required to achieve a goal is part of the _____ process.
document
planning
submittal
transmittal
Developing a schedule on paper helps a supervisor mentally build a project, attempting to _____ that may occur later.
limit material defects
prevent safety breaches
decrease absenteeism
avoid planning errors
“At 3:00 p.m. tomorrow, all plumbing will be installed” is an example of an _____.
objective
allotment
undertaking
assignment
Planners use _____ to determine what labor, equipment, and other means are required for an upcoming project.
stored assets
resource profile
quality control
finished projects
The concept of precedence that is fundamental to a network diagram states that _____.
Activity B is optional according to the budget
Activity B cannot begin until Activity A is complete
Activity A is a higher priority than Activity B
Activity A is scheduled before Activity B
A _____ provides a supervisor with information to direct work efforts efficiently and use resources to their full potential.
bid
log
plan
task
On a schedule, a light line that extends past an activity’s duration represents a(n) _____.
activity float
delayed activity
added activity
completed activity
The time to complete specific activities can reasonably be estimated by various experts including all of the following except _____.
personal experience
equipment manufacturers
subcontractors
OSHA inspectors
Showing how all activities relate to each other is a(n) _____.
major advantage of network diagrams
interviewing skill used by recruiters
technique used to demonstrate logic
part of developing document control
Negotiating a price for the job is part of the _____ stage of planning.
construction
implementation
follow-up
pre-construction
Checking tools in and out through the supervisor has many advantages, including the following, except _____.
producing effective control
reducing wasted time
eliminating worker injuries
maintaining the repair schedule
Supervisors should avoid _____ when conducting job-site meetings.
beginning the meeting late
stating the meeting’s purpose
providing time for questions
repeating items for clarity
Benefits of a bar chart include all of the following except _____.
recording job progress
setting vacation schedules
displaying built-in slack time
helping to create resource profiles