Wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

QUIZ 2

Total questions: 18

Worksheet time: 36mins

Name
Class
Date
1.

For the economic operation, the generator at a power plant operates at ____ Also specify that the penalty factor is the measure of____

a)

Equal loads; line loss

b)

Equal power rating; generation cost

c)

Equal loads; fuel cost

d)

Equal incremental cost; line loss

2.

Calculate the power loss, if power generated by two plants are P1=50 MW and P2=40 MW and the loss coefficients are B11=0.001, B22=0.0025 and B12=-0.0005.

a)

4.5 MW

b)

5.5 MW

c)

6.5 MW

d)

8.5 MW

3.

The incremental fuel cost of two generating units are given by IC1=10+0.2 PG1 IC2=16+0.2 PG2 Where PG1 and PG2 are real power generated by the units. Find the economic allocation for a total load of 170 MW. (neglect transmission line losses)

a)

PG1=60 MW, PG2=110 MW

b)

PG1=80 MW, PG2=90 MW

c)

PG1=100 MW, PG2=70 MW

d)

PG1=120 MW, PG2=50 MW

4.

The economical operation of power system, the effect of increased penalty factor between generating plant and system load current is to

a)

decrease the load on the generating plant

b)

increase load on the plant

c)

hold the plant load constant

d)

increase the power factor

5.

The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by Plant 1: C1=350+6P1+0.004(P1)2C_1=350+6P_1+0.004(P_1)^2 Plant 2: C2=450+aP2+0.003(P2)2C_2=450+aP_2+0.003(P_2)^2 where P1P_1 and P2P_2 are power generated by plant 1 and plant 2, respectively, in MW and aa is constant. The incremental cost of power ( λ\lambda ) is 8 rupees per MWh. The two thermal power plants together meet the total power demand of 550 MW.

a)

200, 350

b)

250, 300

c)

325, 225

d)

350, 200

6.

The incremental cost characteristics of two generators delivering a total load of 230 MW are as follows: IC1=2.4+0.01P1 IC2=2+0.02P2. The ratio of P1/P2 is:

a)

0.6429

b)

2

c)

1

d)

1.55

7.

Unit commitment in power systems primarily deals with

a)

Determining generator voltage levels

b)

Scheduling which generating units will be ON/OFF

c)

Real-time frequency regulation

d)

Reserving fuel for generators

8.

Which of the following constraints is NOT part of unit commitment?

a)

Minimum up-time

b)

Minimum down-time

c)

Ramp rate limits

d)

Per-unit conversion

9.

In thermal plants, minimum up-time constraint means

a)

A unit must remain OFF for a fixed duration

b)

A unit must remain ON for a fixed duration once started

c)

A unit cannot exceed maximum power

d)

A unit must maintain constant frequency.

10.

Which method of load flow analysis is most commonly used in practical power systems?

a)

Gauss–Seidel method

b)

Newton–Raphson method

c)

Fast Decoupled Load Flow

d)

None of the above

11.

The Fast Decoupled Load Flow (FDLF) method assumes

a)

Voltage magnitudes vary greatly

b)

R/X ratio is very high

c)

P–δ and Q–|V| are weakly coupled

d)

No reactive power variation

12.

Which of the following is NOT an advantage of Newton–Raphson method?

a)

Fast convergence

b)

Good for large systems

c)

Low memory requirements

d)

Robustness

13.

Line flows are computed after load flow solution using

a)

Z-bus matrix

b)

Y-bus matrix

c)

Jacobian matrix

d)

Newton coefficients

14.

A single-machine infinite bus (SMIB) system assumes

a)

Both machine and grid have finite inertia

b)

Infinite bus has constant voltage and frequency

c)

No mechanical power input

d)

No electrical power output

15.

The swing equation represents

a)

Voltage dynamics

b)

Rotor angle dynamics of a synchronous machine

c)

Load variations

d)

Transformer flux balance

16.

For a system with n buses, the Z-bus order is

a)

n × n

b)

(n-1) × (n-1)

c)

n × (n-1)

d)

2n × 2n

17.

The diagonal element of Z-bus represents

a)

Line admittance

b)

Self-impedance of that bus

c)

Generator reactance

d)

Shunt capacitance

18.

Z-bus building algorithm is based on

a)

Gauss elimination

b)

Gauss–Seidel iteration

c)

Adding elements using bus building approach

d)

Newton method