WorksheetsDay 72-Dec 6-worksheet-Diploma-Estimation terms part 1
Total questions: 15
Worksheet time: 9mins
Which of the following is not included in the “Data for Estimation”?
Detailed specifications
Scaled drawings
Unit costs
Contractor’s profit
Earnest Money Deposit (EMD) is generally fixed at:
10% of estimated cost
0.5% of estimated cost
1.5–2% of estimated cost
3–5% of estimated cost
Contractor’s profit is usually taken as:
2%
3–5%
8%
10%
Which of the following items is commonly treated as a lumpsum item?
Brickwork
Earthwork excavation
Electrical fittings installation
RCC roof slab
Work charged establishment includes:
Permanent government staff
Temporary staff whose salaries are charged to the work
Staff responsible for issuing tenders only
Administrative approval authorities
Contingencies cover incidental and miscellaneous expenses in an estimate.
True
False
Centage charges are also known as “tender scrutiny charges.”
True
False
If rate and amount columns in an abstract estimate are left blank, the document becomes a (a) .
Work charged establishment salaries are drawn from the (a) amount allotted for the project.
Contingencies typically cover (a) expenses of miscellaneous character.
Centage charges are also known as supervision charges.
True
False
In building estimates, internal electrification typically accounts for ________ % of the building cost. Choose the correct percentage.
2%
5%
8%
18%
Water supply and sanitary provisions are generally allotted ________ % of the estimated cost. Choose the correct percentage.
2%
5%
8%
18%
A technical sanction represents final approval of detailed designs and estimates
True
False
MATCH SET— Plans & Their Purpose. Match each item on the left with its correct purpose on the right.
Project
Complete scheme with designs & estimates
Site Plan
Shows building orientation
Layout Plan
Illustrates overall structure and services
Index Plan
Features of large-scale works