Day 86-Dec 23-worksheet-Btech-PERT&CPM

Total questions: 15

Worksheet time: 10mins

Name
Class
Date
1.

In PERT analysis, the expected time of an activity is calculated using the formula:

a)

(to+tm+tp)/3(t_o + t_m + t_p) / 3

b)

(to+tp)/2(t_o + t_p) / 2

c)

(to+4tm+tp)/6(t_o + 4t_m + t_p) / 6

d)

(to+3tm+tp)/5(t_o + 3t_m + t_p) / 5

2.

Which of the following correctly represents the standard deviation of an activity time in PERT?

a)

tptot_p - t_o

b)

(tpto)/3(t_p - t_o) / 3

c)

(tpto)/6(t_p - t_o) / 6

d)

(tptm)/6(t_p - t_m) / 6

3.

In a PERT network, if an event has multiple incoming activities, the earliest expected time of the event is obtained by:

a)

Taking the minimum of incoming times

b)

Taking the average of incoming times

c)

Taking the maximum of incoming times

d)

Taking the sum of incoming times

4.

Slack of an event is defined as the difference between:

a)

EST and EFT

b)

LST and LFT

c)

Latest allowable time and earliest expected time

d)

Total float and free float

5.

An activity having zero float is classified as:

a)

Sub-critical activity

b)

Super-critical activity

c)

Dummy activity

d)

Critical activity

6.

Which of the following floats represents delay without affecting the succeeding activity?

a)

Total float

b)

Free float

c)

Independent float

d)

Interfering float

7.

CPM is best suited for:

a)

Research-oriented projects

b)

Probabilistic projects

c)

Repetitive construction projects

8.

In PERT, each activity is assumed to follow a beta probability distribution.

a)

True

b)

False

9.

Negative slack indicates that the project is ahead of schedule.

a)

True

b)

False

10.

Assertion (A): PERT uses three time estimates for each activity. Reason (R): PERT follows a deterministic approach for project scheduling. Choose the correct option.

a)

A is true, R is true and R explains A

b)

A is true, R is false

c)

A is false, R is true

d)

A is false, R is false

11.

PERT stands for (a)   .

12.

The pessimistic time represents the (a)   possible duration under worst conditions.

13.

The earliest time by which an event may occur is called (a)   .

14.

Slack equal to zero indicates a (a)   event.

15.

An activity with negative float is known as a (a)   activity.