The responsibility that distinguishes a project manager from a project superintendent is that the project manager
generally works on site
supervises craft workers
is responsible for project planning
coordinates the work of subcontractors
Which of these statements describes a work breakdown structure?
Diagrams tasks based on their longest path through the network.
Sets up project tasks in a top-down structure.
Identifies positions in the organization structure.
Identifies project activities that are unlikely to complete on schedule.
The four elements of an effective communication plan are communications planning, information distribution, administrative closure, and _____.
performance reporting
project planning
performance enhancement
work breakdown structure
A project manager who acts in a manner that meets accepted standards of conduct is considered to be _____.
antisocial
efficient
ethical
capable
Which of these tasks is generally performed during the development phase of a project?
Development of final drawings
Feasibility study
Final inspection
Obtaining bids from subcontractors
Project schedules are generally developed during which phase of a project?
Bidding
Construction
Closeout
Pre-construction
When developing the project schedule, the project manager or estimator should _____.
consult with the owner's capital projects officer
modify an existing schedule that is similar in scope
consult with members of the project team
reject input from other sources
Which of these tasks is undertaken during mobilization?
Schedule development
Review of estimates
Setting up field offices
Issuing purchase orders
Two documents that are submitted for project closeout are _____.
cost summary report and punch list
punch list and original drawings
list of change orders and lien release
as-built drawings and completed punch list
The delivery system in which one company performs design, engineering, management, and construction services is _____.
design-build
CM
EPC
GC