Jan Mock recap

Total questions: 20

Worksheet time: 10mins

Name
Class
Date
1.

Which item is essential to include when compiling a construction risk assessment for a new school lighting installation?

a)

Cafeteria weekly menu plan

b)

Project marketing slogan draft

c)

Supplier brand preferences list

d)

Hazard identification and description

2.

A step-down transformer is required in the lighting system. What is its primary function in electrical design?

a)

Reduce higher voltage to lower voltage

b)

Increase low voltage to higher voltage

c)

Convert AC power into DC power

d)

Store electrical energy like a battery

3.

Which method can be used to investigate ground conditions before designing a bridge across a valley?

a)

Painting soil surfaces blue

b)

Aerial photography only

c)

Posting an online public survey

d)

Borehole drilling and sampling

4.

When designing the bridge, what is a key benefit of using CAD modelling software?

a)

Eliminate the need for engineers

b)

Guarantee zero construction defects

c)

Visualize and test design iterations

d)

Automatically approve planning permits

5.

During construction, the main contractor and specialists share information via cloud computing. What is one benefit of this approach?

a)

Offline-only document storage method

b)

Removal of all onsite coordination needs

c)

Real-time access to shared project data

d)

Guaranteed cybersecurity without effort

6.

Which action best supports developing a safe system of work before construction begins on multi-storey accommodation blocks?

a)

Ignore hazards until site work starts

b)

Skip planning to meet tight deadlines

c)

Prepare method statements for key activities

d)

Rely solely on subcontractor experience

7.

Before purchasing land for new blocks, which use of Land Registry data most directly helps the university?

a)

Verifying legal ownership and title details

b)

Estimating construction labour productivity

c)

Selecting interior finishes for kitchens

d)

Determining the number of storeys to build

8.

When refurbishing an old building, which advantage of creating a BIM model is most accurate?

a)

Eliminates the need for planning permission

b)

Automatically restores damaged historic materials

c)

Improves clash detection and coordination of services

d)

Guarantees faster construction without delays

9.

For a fast programme on a brownfield housing site, which construction form most reduces on-site labour while maintaining consistent quality?

a)

Traditional brick and block walls built on site

b)

Precast concrete sections and cladding panels

c)

Timber frame with site-applied sheathing

d)

Masonry cavity walls with on-site insulation

10.

Which information should be included in a risk assessment for installing electrical circuits in an industrial unit?

a)

Severity and likelihood of identified hazards

b)

Employee lunch break schedules

c)

Manufacturer logos of cable suppliers

d)

List of paint colours for distribution boards

11.

In an industrial electrical installation, what is a main purpose of transformers?

a)

Converting alternating current to direct current

b)

Changing voltage levels between circuits

c)

Measuring current in protective devices

d)

Storing electrical energy for long periods

12.

Which statement best describes a key reason electrical installations must meet current British Standards on a housing project?

a)

Ensures safety and reduces fire and shock risks

b)

Improves aesthetics of visible wiring and fixtures

c)

Guarantees faster installation with fewer workers

d)

Allows creative layouts without technical constraints

13.

A civil engineering contractor suspects former factory land may be contaminated. Which method is most appropriate to determine contamination?

a)

Conduct a Phase I desk study and soil sampling

b)

Increase site fencing and security patrols

c)

Schedule additional concrete deliveries early

d)

Survey property boundaries with total stations

14.

When producing cost estimates using NRM1, which approach aligns with its requirements?

a)

Lump‑sum guess based on previous project total

b)

Price per square metre without breakdown or notes

c)

Elemental cost planning using standard work breakdown

d)

Hourly labour rates multiplied by random allowances

15.

Why should a manual handling assessment be conducted for brick and block cavity wall construction?

a)

To reduce musculoskeletal injury and choose safe methods

b)

To improve paint finish quality on interior walls

c)

To meet marketing targets for finished house sales

d)

To speed up design approvals with planners

16.

Which performance indicator would best help a not‑for‑profit animal rescue centre manage a new building effectively?

a)

Energy use per square metre monthly

b)

Number of animals adopted annually

c)

Average staff commute distance

d)

Donor satisfaction with outreach events

17.

When surveying a site with a total station, which advantage most improves accuracy during layout?

a)

Automatic level bubble visualization

b)

Real‑time satellite image overlay

c)

Integrated electronic distance measurement

d)

Manual tape measure triangulation

18.

The site plan shows a triangular plot bordered by a river and a railway, with one side measuring 45 m, another side 72 m along the railway, and the included angle between them 100°. Which procedure best estimates the site area?

a)

Divide into two right triangles using 45 m and 72 m legs

b)

Treat as rectangle using 45 m by 72 m dimensions

c)

Apply cosine rule to get third side then triangle area ½ab sin C

d)

Use sine rule to find third side then Heron’s formula

19.

The developer plans phased conversion and aims to lease some apartments while upper floors are still being fitted. On a constrained site with limited storage by a river and railway, what is a key benefit of using just-in-time delivery?

a)

Allows bulk buying to lower material unit prices

b)

Eliminates the need for safety reviews entirely

c)

Guarantees faster structural completion dates

d)

Reduces onsite inventory and frees limited space

20.

Which design decision best demonstrates using climatic data to enhance resident comfort while maintaining environmental control in a warm, humid climate?

a)

Seal units tightly to eliminate outdoor air exchange

b)

Use black roofing to absorb maximum solar radiation

c)

Orient buildings to capture prevailing breezes for cross-ventilation

d)

Increase glazing on west façades for evening light