WorksheetsPage 1
Total questions: 15
Worksheet time: 8mins
Which listed task involves excavation rather than construction of concrete structures?
Armature installation measured in
Concrete base B25 construction measured in cubic meters
Foundation pit digging measured in cubic meters
Concrete B30 placement measured in cubic meters
Bitumen B15 pouring measured in cubic meters
Which pipeline activity would most directly increase the total trench length recorded as 14.13 m?
Applying extra waterproofing layers
Adding more armature bars by weight
Pouring bitumen B15 into joints
Increasing concrete B25 volume used
Excavating additional trench segments
If armature totals 1486.44 kg for the pipeline and 343.34 kg for head and wing sections combined, what planning choice reduces total steel demand?
Add backfill volume to stabilize foundations
Increase waterproofing area in both sections
Raise concrete grade from B25 to B30 throughout
Optimize reinforcement layout to eliminate redundancy
Decrease trench length while maintaining section count
A planner wants to verify volumes for the wing section. Which value corresponds to concrete B25 used there?
1.08 cubic meters for wing concrete
1.05 cubic meters for head concrete
151.40 kilograms of armature
97.43 square meters trench waterproofing
10.68 square meters waterproofing
What is the unit used to measure the quantity of rebar in the schedule?
Kilograms (kg)
Meters (m)
Square meters (m²)
Cubic meters (m³)
Identify the correct thickness specified for the protective layer against water ingress and garage moisture.
40 mm
150 mm
400 mm
200 mm
Which entry refers to a drainage slope with a specified height?
Drain slope h=20 mm
Drain slope h=40 mm
Drain slope h=400 mm
Drain slope h=200 mm
Select the correct total quantity for rebar as recorded in the table.
969.38 kg
59.25 kg
3.94 kg
29.40 kg
The drawings specify a concrete base under the culverts. For historical drainage works, why was a concrete base preferred over compacted soil alone?
Resist settlement and maintain alignment
Allow faster vegetation growth around pipes
Reduce material transport costs to site
Increase the pipe’s acoustic properties
Identify the primary purpose of the plan labeled “ПЛАН 1:100” shown in the diagram with hexagonal hatching and central conduit.
Drafting a railway signal foundation
Planning a drainage culvert structure
Mapping a medieval city wall segment
Designing a fortified bridge abutment
One note indicates “Төмөр бетон хоолойн арматурын хамгаалалт нь 50мм байна.” What is the implication for reinforcement detailing?
Provide 50 mm concrete cover
Limit bar lap to 50 mm
Space stirrups at 50 mm
Use 50 mm diameter rebar
Why would standards like “MNS 5829:2007” be cited in a civil plan of this type?
Avoid calculating structural loads
Increase drawing aesthetic quality
Reduce the need for on-site testing
Ensure compliance with national codes
The plan dimensions indicate “2000” on each end flared section. Interpreting scale 1:100, what real-world length does 2000 represent?
Two hundred millimeters length
Twenty meters actual length
Two meters actual length
Two hundred meters actual length
Identify the most plausible material referenced by the symbol "Ø1,0φ төмөрбетон хоолой" appearing near roles and notes.
Cast iron bridge deck plate, 1.5 m
Timber flume element, 2.0 m span
Pressed clay sewer tile, 0.5 m width
Reinforced concrete pipe, 1.0 m diameter
Woven reed culvert segment
If the project sheet is dated "2023 оны 01 сар", what administrative implication does this have for document control?
It defines the fiscal year’s end date
It records the average winter temperature
It indicates the drafting month for versioning
It states the material delivery deadline
It sets the timeline for public holidays
