Critical Path Method (CPM)

Critical Path Method (CPM)

Assessment

Flashcard

Professional Development

University

Practice Problem

Hard

Created by

Wayground Content

FREE Resource

Student preview

quiz-placeholder

11 questions

Show all answers

1.

FLASHCARD QUESTION

Front

What is critical path method (CPM)?

Back

a step-by-step project management technique for process planning that defines critical and non-critical tasks.

2.

FLASHCARD QUESTION

Front

What is CPM?

Back

Critical path method

3.

FLASHCARD QUESTION

Front

Critical path in network gives ___ to complete the project.

Back

Shortest time

4.

FLASHCARD QUESTION

Front

In Critical Path Method, the project completion period is the EF of last activities.

Back

True

5.

FLASHCARD QUESTION

Front

Changing the duration of a critical activity will not affect the overall completion time.

Back

False

6.

FLASHCARD QUESTION

Front

The starting activities that have no predecessor cannot be carried out in parallel.

Back

False

7.

FLASHCARD QUESTION

Front

Changing the duration of a non-critical activity will not affect the overall completion time, provided the revised float is positive.

Back

True

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?