1.

FLASHCARD QUESTION

Front

If the duration for Activity I changes to 4 days instead of 2 days, what is the critical path in the project case found below?

Back

27 days

2.

FLASHCARD QUESTION

Front

What is the term for an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level?

Back

Rolling Wave Planning

3.

FLASHCARD QUESTION

Front

The logical relationships under Precedence Diagramming Method (PDM) include: Finish-to-start, Start-to-finish, Start-to-start, All of these

Back

All of these

4.

FLASHCARD QUESTION

Front

What type of dependency is identified in the activity of obtaining a safety certificate from the government for launching a soft drink?

Back

Mandatory dependencies

5.

FLASHCARD QUESTION

Front

Reserve Analysis is a technique for:

Back

Estimate Activity Durations

6.

FLASHCARD QUESTION

Front

Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique?

Back

Resource Leveling

7.

FLASHCARD QUESTION

Front

To crash a schedule you should: Put extra resources on those tasks that are on the critical path.

Back

Put extra resources on those tasks that are on the critical path.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?