

Unit 4 Test 3 of 3
Flashcard
•
Business
•
9th - 12th Grade
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Student preview

10 questions
Show all answers
1.
FLASHCARD QUESTION
Front
If the duration for Activity I changes to 4 days instead of 2 days, what is the critical path in the project case found below?
Back
27 days
2.
FLASHCARD QUESTION
Front
What is the term for an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level?
Back
Rolling Wave Planning
3.
FLASHCARD QUESTION
Front
The logical relationships under Precedence Diagramming Method (PDM) include: Finish-to-start, Start-to-finish, Start-to-start, All of these
Back
All of these
4.
FLASHCARD QUESTION
Front
What type of dependency is identified in the activity of obtaining a safety certificate from the government for launching a soft drink?
Back
Mandatory dependencies
5.
FLASHCARD QUESTION
Front
Reserve Analysis is a technique for:
Back
Estimate Activity Durations
6.
FLASHCARD QUESTION
Front
Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique?
Back
Resource Leveling
7.
FLASHCARD QUESTION
Front
To crash a schedule you should: Put extra resources on those tasks that are on the critical path.
Back
Put extra resources on those tasks that are on the critical path.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?