FLASHCARD QUESTION

Front

What is an activity in project management?

Back

An activity is an element of the project that requires time. It may or may not require resources.

2.

FLASHCARD QUESTION

Front

What are parallel activities?

Back

Parallel activities are activities that can take place at the same time, if the manager wishes. However, the manager may choose to have parallel activities not occur simultaneously.

3.

FLASHCARD QUESTION

Front

What is a burst activity?

Back

A burst activity is an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it).

4.

FLASHCARD QUESTION

Front

What is a merge activity?

Back

A merge activity is an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it).

5.

FLASHCARD QUESTION

Front

What is a path in project management?

Back

A path is a sequence of connected, dependent activities.

6.

FLASHCARD QUESTION

Front

What is the critical path?

Back

The critical path is the path(s) with the longest duration through the network; if an activity on the path is delayed, the project is delayed the same amount of time.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?