1.

FLASHCARD QUESTION

Front

What should be installed immediately above any stop valve?

Media Image

Back

Drain-off valve

2.

FLASHCARD QUESTION

Front

In this system all cold water taps supply wholesome water. What type of system is this?

Back

direct

3.

FLASHCARD QUESTION

Front

What is this called? Options: Circular saw, Big round saw, Pad saw, Hole saw

Media Image

Back

Hole saw

4.

FLASHCARD QUESTION

Front

What is the purpose of this tool?

Media Image

Back

To make holes for pipe connections in CWSC

5.

FLASHCARD QUESTION

Front

What pipe size should be used for the cold feed to the hot water cylinder? Options: 10mm, 20mm, 15mm, 22mm

Back

22mm

6.

FLASHCARD QUESTION

Front

In a direct system, how many litres of water should the cold water storage cistern hold to supply the hot water cylinder?

Back

100-150 litres

7.

FLASHCARD QUESTION

Front

In an indirect system, what is the minimum amount of water required for the CWSC?

Back

230 litres

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?