As the Scrum Master, what is the BEST course of action that aligns with the “Fail Fast” mindset when a new feature is technically flawed and poorly aligned with customer expectations? Options: Continue working on the feature until the sprint ends to avoid disrupting the team’s flow, Immediately escalate the issue to the project sponsor and pause all development activities, Use the daily stand-up or next retrospective to discuss the failure and improve future estimates, Facilitate a quick discussion with the team to inspect the issue and adapt based on feedback.
Lesson 5 - (Topic A) - PMP

Flashcard
•
Professional Development
•
Professional Development
•
Hard
Quizizz Content
FREE Resource
Student preview

4 questions
Show all answers
1.
FLASHCARD QUESTION
Front
Back
Facilitate a quick discussion with the team to inspect the issue and adapt based on feedback
Answer explanation
The “Fail Fast” principle encourages:
Early testing and failure detection
Rapid adaptation or pivoting
Minimizing waste of time, money, and effort
2.
FLASHCARD QUESTION
Front
What Agile practice or mindset does showing two different button versions to different user groups simultaneously to gather usage data BEST reflect?
Back
A/B Testing to validate assumptions through experimentation
Answer explanation
A/B testing is an Agile-friendly technique that allows teams to test assumptions and validate which version performs better, using real-time user feedback.
This practice supports hypothesis-driven development and data-informed decisions, key Agile principles in product innovation.
3.
FLASHCARD QUESTION
Front
What is the PRIMARY purpose of the retrospective meeting in Agile projects?
Back
To inspect the team’s process and identify improvements.
Answer explanation
The Sprint Retrospective is focused on continuous improvement. The team inspects how they worked, discusses what went well and what didn’t, and identifies actionable steps for better performance in future sprints.
4.
FLASHCARD QUESTION
Front
Which project document should you refer to for evaluating the team's current mitigation strategies and readiness to act on quality-related risks? Options: Quality Management Plan, Risk Register, Lessons Learned Register, Issue Log
Back
Risk Register
Answer explanation
The Risk Register helps assess current continuous improvement measures by showing how the team plans to monitor, mitigate, or respond to threats to project quality.
Similar Resources on Quizizz
7 questions
2024 ASPBI & 2024 SICT

Flashcard
•
KG - University
8 questions
AMS - PSSST - Refresher

Flashcard
•
Professional Development
5 questions
Subpart P Excavations

Flashcard
•
Professional Development
7 questions
Present Perfect Business Speaking

Flashcard
•
Professional Development
8 questions
Automotive Tools & Equipment Identification

Flashcard
•
KG - University
10 questions
Affirmative Action Scenarios

Flashcard
•
Professional Development
8 questions
LS Unit 7 Team Building Vocabulary

Flashcard
•
University
7 questions
FAll Protection ll

Flashcard
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade