What is the formula for calculating the number of services per vehicle load (N)?
Back
N = (C x D)/W, where C = Vehicle capacity (m3), D = Waste density (kg/m3), W = Waste generation/residence (kg/service)
2.
FLASHCARD QUESTION
Front
How is the time required to collect one load (E) calculated?
Back
E = N x L, where L = Loading time/residence, including on-route travel.
3.
FLASHCARD QUESTION
Front
What factors are considered in estimating the number of loads (n) a crew can collect in a day?
Back
Workday length (t), administrative and break time (t1), hauling and travel time (t2), and collection route time (t3).
4.
FLASHCARD QUESTION
Front
What is the formula for administrative and break time (t1)?
Back
t1 = A + B, where A = Administrative time and B = Time for breaks and lunch.
5.
FLASHCARD QUESTION
Front
What does the formula for hauling and other travel time (t2) include?
Back
t2 = (n x H) - f + G + J, where H = Time to travel to disposal site, f = Time to return from site to route, G = Time to travel from staging garage to route, J = Time to return from disposal site to garage.
6.
FLASHCARD QUESTION
Front
How is the time spent on the collection route (t3) calculated?
Back
t3 = n x E.
7.
FLASHCARD QUESTION
Front
What is the formula for calculating the length of the workday (t)?
Back
t = t1 + t2 + t3.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?