1.

SLIDE QUESTION

1 min • 1 pt

2.

SLIDE QUESTION

1 min • 1 pt

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the critical path in a project represent?

The sequence of optional tasks

The longest projected timeline for optional activities

The sequence of activities that must be completed on time for project completion

The list of activities that can be delayed without affecting the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the critical path determined?

By lining up the longest mandatory dependent tasks

By random assignment of tasks

By choosing the tasks with the least cost

By selecting tasks with the highest quality rating

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After completing the video based critical path, what is the earliest start time for last activity in this project?

Day 16

Day 12

Day 19

Undetermined

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the absolute latest day activity C can begin without causing a delay?

Day 3

Day 5

Day 11

Day 9

7.

CATEGORIZE QUESTION

3 mins • 1 pt

What is the critical path? Drag the activities in order.​

Groups:

(a) IN Critical Path

,

(b) Not In Critical Path

Activity H

Activity E

Activity B

Activity G

Activity A

Activity F

Activity D

Activity C

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?