24-25 PM Critical Path Lesson
Interactive Video
•
Business
•
9th - 12th Grade
•
Practice Problem
•
Medium
Bobbie Jones
Used 18+ times
FREE Resource
11 questions
Show all answers
1.
SLIDE QUESTION
1 min • 1 pt
2.
SLIDE QUESTION
1 min • 1 pt
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the critical path in a project represent?
The sequence of optional tasks
The longest projected timeline for optional activities
The sequence of activities that must be completed on time for project completion
The list of activities that can be delayed without affecting the project
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is the critical path determined?
By lining up the longest mandatory dependent tasks
By random assignment of tasks
By choosing the tasks with the least cost
By selecting tasks with the highest quality rating
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After completing the video based critical path, what is the earliest start time for last activity in this project?
Day 16
Day 12
Day 19
Undetermined
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the absolute latest day activity C can begin without causing a delay?
Day 3
Day 5
Day 11
Day 9
7.
CATEGORIZE QUESTION
3 mins • 1 pt
What is the critical path? Drag the activities in order.
Groups:
(a) IN Critical Path
,
(b) Not In Critical Path
Activity E
Activity C
Activity A
Activity F
Activity D
Activity H
Activity G
Activity B
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?