
Lesson 5 ITPM: Project Management Network Diagrams
Presentation
•
Education
•
University
•
Practice Problem
•
Medium
Jerry Jackson Bent
Used 11+ times
FREE Resource
46 Slides • 7 Questions
1
Project Management Network Diagrams
2
3
4
5
6
7
8
According to Tarver & Aditham, from Forbes advisor, work breakdown structure (WBS) and Critical Path Method (CPM) are in the top 7 essential project management techniques in 2024.
You can read the full article here: https://www.forbes.com/advisor/business/project-management-techniques/#1_work_breakdown_structure_wbs_section
Why WBS and Critical Path Analysis?
9
10
11
12
13
14
15
16
17
18
https://www.knowledgehut.com/blog/project-management/what-is-network-diagram#what%20-is-a-project
19
20
21
22
https://www.youtube.com/watch?v=rxGcV0tuxRU&t=251s&ab_channel=OnlinePMCourses-MikeClayton
23
Fill in the Blanks
Type answer...
24
Multiple Choice
The Critical Path Method was developed in the late ____
1940s
1950s
1960s
25
Multiple Choice
The Critical Path Method was developed by Morgan R. Walker and _______.?
James E. Kelley
Morgan Freeman
Andrew Paul
26
Multiple Choice
The critical path” represents the shortest time possible for completing a project.
True
False
27
Multiple Choice
As explained in the video the critical path method is a ...
Project scheduling tool
Project management methodology
Project Modelling Methodology
28
Multiple Choice
The critical path method was inspired by a competing methodology called ...
PERT
BERT
DERT
29
Multiple Choice
In critical path method, we specify each activity using the ...
Work Breakdown Structure (WBS)
Project plan
PERT method
30
31
32
33
34
35
36
37
38
WBS
Start by examining the WBS, which should detail all the tasks required to complete the project. Each task should have a defined duration and dependencies with other tasks, if applicable.
Review the Work Breakdown Structure (WBS):
Step 1
39
Determine the dependencies between tasks. Tasks can be either sequential (where one task must be completed before another can start) or parallel (where tasks can be executed simultaneously).
In our WBS, Tasks AB & D do not have any predecessor activities
Identify Task Dependencies:
Step 2
Place a start symbol (this is optional).Tasks A, B and D can start at the same time since they do not depend on any preceding task. Align all 3 tasks vertically.
40
Since tasks A, B and D have commenced, the next activity is 'C' which is dependent on A and B. Place activity 'C' where it is easy to draw links from both tasks without possibility of crossing any lines
Identify and Position Next Task:
Step 3
41
Move alphabetically and place any activity that has already been inserted in the chart. Make sure to position activities strategically so its easy to draw arrows to predecessors without intersecting any other arrow.
Step 4
42
Link with arrows. Take note of predecessor activities.
Step 5
43
Insert estimated durations or days for each activity.
Step 6
44
C is dependent on A and B to be completed before it can start. Therefore, both activities would be completed on day 4 so the earliest possible time C can start is 4. The earliest finish time for C will be the sum of the earliest start (4) and number of days required to complete activity C (5) [4+5=9]. Apply same steps to F. ES for F is 1 and EF will be 1+2=3
Step 7
45
E is dependent on C so the ES is 9. EF will therefore be 9+5=14. G is dependent on E & F to be completed before it can start. Therefore, ES is 14 and EF will be 14+5=19. H is dependent on G to be completed before it can start. Hence, ES will be 19 and EF will be 19+6=25
Step 8
Overall duration of this project is 25days
46
Starting from the end of the network diagram with activity H, coming from G, this is a converging task coming at the end so the values for LS and LF will be the same as ES and EF i.e 19 and 25. For activity G, the latest possible finish is 19 because activity H starts on day 19. LS for G will be 19 – 5 (duration of activity G) = 14. Day 14 is the latest time that G can start for the project to remain on track
Step 9
Now we will start the second pass to find latest start time and latest finish time
47
LF for activity E is 14. LS will be 14-5=9. For activity F, LF is 14 because activity E has a longer duration of 14 which G also depends on to be completed before it starts. LS for ‘F’ will be 14-2=12. For activity D, LF will be 12 and LS will be 12-1=11. Activity C will have a latest finish of 9 and LS will be 9-5=4. For activity B, LF will be 4 and LS will be 4-3=1. Finally for A, LF will be 4 and LS will be 4-4 = 0.
Step 10
Apply the same approach to determine E to A
48
Use the Total slack formular to calculate total slack for each activity. H = 25-25=0, G=19-19=0, E=14-14=0, C=9-9=0, A = 4-4=0. F=14-3=11, D=12-1=11, B=4-3=1
Step 11
Calculate total slack or slippage. This will be used to determine the critical path.
49
From the network diagram, take note of the path that has 0(zeros) as all its total slack time. The path A, C, E, G and H is our critical path. This implies that all the activities along this path are crucial in ensuring that the project is completed on time. Having zero slack or slippage means we have no leeway with regards the schedule of the project. On the other hand, the path B, D and F has a lot of leeway. E.g, Task D and F has up to 11days slack to be completed even though they only require 1 and 2 days respectively to be completed.
Step 12
Determining the critical path
50
51
52
53
Project Management Network Diagrams
Show answer
Auto Play
Slide 1 / 53
SLIDE
Similar Resources on Wayground
46 questions
Climate and Effects of Climate Change
Presentation
•
University
48 questions
BIO111 Chp 15 Genes and Proteins
Presentation
•
University
48 questions
KONSEP DASAR IPA GAYA DAN PERCEPATAN
Presentation
•
University
48 questions
POPULAR MEMBER SERVICES DIAGNOSTICS, HOSPITILIZATION AND SURGERY
Presentation
•
KG
47 questions
Ser + Adjetivos
Presentation
•
12th Grade
45 questions
TOEFL "Forum Reboan"
Presentation
•
University
47 questions
TOEFL Written Expression
Presentation
•
University
48 questions
Some/Any/Every/No Compounds
Presentation
•
University
Popular Resources on Wayground
16 questions
Grade 3 Simulation Assessment 2
Quiz
•
3rd Grade
19 questions
HCS Grade 5 Simulation Assessment_1 2526sy
Quiz
•
5th Grade
10 questions
Cinco de Mayo Trivia Questions
Interactive video
•
3rd - 5th Grade
17 questions
HCS Grade 4 Simulation Assessment_2 2526sy
Quiz
•
4th Grade
24 questions
HCS Grade 5 Simulation Assessment_2 2526sy
Quiz
•
5th Grade
13 questions
Cinco de mayo
Interactive video
•
6th - 8th Grade
20 questions
Math Review
Quiz
•
3rd Grade
30 questions
GVMS House Trivia 2026
Quiz
•
6th - 8th Grade
Discover more resources for Education
55 questions
Post Malone Addtion (Tres)
Quiz
•
12th Grade - University
20 questions
Disney Trivia
Quiz
•
University
50 questions
AP Biology Exam Review 2017
Quiz
•
11th Grade - University
24 questions
5th Grade Math EOG Review
Quiz
•
KG - University
12 questions
Star Wars Trivia - Easy
Quiz
•
KG - University
215 questions
8th Physical Science GA Milestones Review
Quiz
•
KG - University
40 questions
Famous Logos
Quiz
•
7th Grade - University
14 questions
(5-3) 710 Mean, Median, Mode & Range Quick Check
Quiz
•
6th Grade - University