Search Header Logo
Lesson 5 ITPM: Project Management Network Diagrams

Lesson 5 ITPM: Project Management Network Diagrams

Assessment

Presentation

Education

University

Practice Problem

Medium

Created by

Jerry Jackson Bent

Used 11+ times

FREE Resource

46 Slides • 7 Questions

1

Project Management Network Diagrams

media

2

media

3

media

4

media

5

media

6

media

7

media

8

According to Tarver & Aditham,  from Forbes advisor, work breakdown structure (WBS) and Critical Path Method (CPM) are in the top 7 essential project management techniques in 2024.

You can read the full article here:  https://www.forbes.com/advisor/business/project-management-techniques/#1_work_breakdown_structure_wbs_section

Why WBS and Critical Path Analysis?

media

9

media

10

media

11

media

12

media

13

media

14

media

15

media

16

media

17

media

18

media

​https://www.knowledgehut.com/blog/project-management/what-is-network-diagram#what%20-is-a-project

19

media

20

media

21

media

22

media

​https://www.youtube.com/watch?v=rxGcV0tuxRU&t=251s&ab_channel=OnlinePMCourses-MikeClayton

23

Fill in the Blank

Work breakdown structure (WBS) is a project management technique that segments larger projects into more manageable ___________. [OPTIONS: Projects | Deliverables | Teams]

24

Multiple Choice

The Critical Path Method was developed in the late ____

1

1940s

2

1950s

3

1960s

25

Multiple Choice

The Critical Path Method was developed by Morgan R. Walker and _______.?

1

James E. Kelley

2

Morgan Freeman

3

Andrew Paul

26

Multiple Choice

The critical path” represents the shortest time possible for completing a project.

1

True

2

False

27

Multiple Choice

As explained in the video the critical path method is a ...

1

Project scheduling tool

2

Project management methodology

3

Project Modelling Methodology

28

Multiple Choice


The critical path method was inspired by a competing methodology called ...

1

PERT

2

BERT

3

DERT

29

Multiple Choice

In critical path method, we specify each activity using the ...

1

Work Breakdown Structure (WBS)

2

Project plan

3

PERT method

30

media

31

media

32

media

33

media

34

media

35

media

36

media

37

media

38

WBS

Start by examining the WBS, which should detail all the tasks required to complete the project. Each task should have a defined duration and dependencies with other tasks, if applicable.

Review the Work Breakdown Structure (WBS):

Step 1

media

39

Determine the dependencies between tasks. Tasks can be either sequential (where one task must be completed before another can start) or parallel (where tasks can be executed simultaneously).

In our WBS, Tasks AB & D do not have any predecessor activities

Identify Task Dependencies:

Step 2

media

​Place a start symbol (this is optional).Tasks A, B and D can start at the same time since they do not depend on any preceding task. Align all 3 tasks vertically.

media

40

Since tasks A, B and D have commenced, the next activity is 'C' which is dependent on A and B. Place activity 'C' where it is easy to draw links from both tasks without possibility of crossing any lines

Identify and Position Next Task:

Step 3

media
media

41

Move alphabetically and place any activity that has already been inserted in the chart. Make sure to position activities strategically so its easy to draw arrows to predecessors without intersecting any other arrow.

Step 4

media
media

42

Link with arrows. Take note of predecessor activities.

Step 5

media
media

43

Insert estimated durations or days for each activity.

Step 6

media
media

44

C is dependent on A and B to be completed before it can start. Therefore, both activities would be completed on day 4 so the earliest possible time C can start is 4. The earliest finish time for C will be the sum of the earliest start (4) and number of days required to complete activity C (5) [4+5=9]. Apply same steps to F. ES for F is 1 and EF will be 1+2=3

Step 7

media
media

45

E is dependent on C so the ES is 9. EF will therefore be 9+5=14. G is dependent on E & F to be completed before it can start. Therefore, ES is 14 and EF will be 14+5=19. H is dependent on G to be completed before it can start. Hence, ES will be 19 and EF will be 19+6=25

Step 8

media
media

Overall duration of this project is 25days

46

Starting from the end of the network diagram with activity H, coming from G, this is a converging task coming at the end so the values for LS and LF will be the same as ES and EF i.e 19 and 25. For activity G, the latest possible finish is 19 because activity H starts on day 19. LS for G will be 19 – 5 (duration of activity G) = 14. Day 14 is the latest time that G can start for the project to remain on track

Step 9

media

Now we will start the second pass to find latest start time and latest finish time

media

47

LF for activity E is 14. LS will be 14-5=9. For activity F, LF is 14 because activity E has a longer duration of 14 which G also depends on to be completed before it starts. LS for ‘F’ will be 14-2=12. For activity D, LF will be 12 and LS will be 12-1=11. Activity C will have a latest finish of 9 and LS will be 9-5=4. For activity B, LF will be 4 and LS will be 4-3=1. Finally for A, LF will be 4 and LS will be 4-4 = 0.

Step 10

media

Apply the same approach to determine E to A

media

48

Use the Total slack formular to calculate total slack for each activity. H = 25-25=0, G=19-19=0, E=14-14=0, C=9-9=0, A = 4-4=0. F=14-3=11, D=12-1=11, B=4-3=1

Step 11

media

Calculate total slack or slippage. This will be used to determine the critical path.

media

49

From the network diagram, take note of the path that has 0(zeros) as all its total slack time. The path A, C, E, G and H is our critical path. This implies that all the activities along this path are crucial in ensuring that the project is completed on time. Having zero slack or slippage means we have no leeway with regards the schedule of the project. On the other hand, the path B, D and F has a lot of leeway. E.g, Task D and F has up to 11days slack to be completed even though they only require 1 and 2 days respectively to be completed.

Step 12

media

Determining the critical path

media

50

media

51

media

52

media

53

media

Project Management Network Diagrams

media

Show answer

Auto Play

Slide 1 / 53

SLIDE