Search Header Logo
Module 04: Construction Contract & Risk Management

Module 04: Construction Contract & Risk Management

Assessment

Presentation

Professional Development

Professional Development

Practice Problem

Hard

Created by

Afghanistan Center

FREE Resource

67 Slides • 32 Questions

1

media

2

media

3

media

4

media

5

media

6

7

media

8

media

9

media

10

media

11

media

12

media

13

media

14

media

15

media

16

Multiple Choice

Which of the following activities is most likely performed during the 'Pre-Award' phase of the contract life cycle?

1

Finalizing claims and changes

2

Evaluating market feasibility

3

Selecting the contract type and developing bidding strategy

4

Conducting lessons learned

17

Multiple Choice

You are managing a construction project and your team is preparing bid documents, selecting the delivery method, and defining the contract type. Which phase of the contract life cycle are you currently in?

1

Pre-Award

2

Proposal Process

3

Contract Execution and Management

4

Close-out

18

Multiple Choice

A project manager is reviewing contractor performance and ensuring that compliance requirements are being met. Which phase of the contract life cycle does this activity belong to?

1

Contract Close-out

2

Contract Execution and Management

3

Proposal Process

4

Discovery

19

media

20

media

21

media

22

media

23

Multiple Choice

Which contract clause defines how and when the contractor will receive payments?

1

Liquidated Damages

2

Indemnity

3

Termination Clause

4

Payment

24

Multiple Choice

A subcontractor claims for additional payment due to unexpected delays, but the contractor refuses, citing that the claim was filed months after the project ended. Which clause would most likely be used to resolve this dispute?

1

Termination Clause

2

Time-Barred Claims

3
4

25

Multiple Choice

During construction, a sudden design change increases both cost and project duration. What clause should the project manager refer to first?

1

Change / Change Order

2

Liquidated Damages

3

Indemnity

4

Payment

26

media

27

media

28

media

29

media

30

media

31

media

32

media

33

media

34

Multiple Choice

In which delivery method does a single entity handle both design and construction, resulting in faster delivery and single-point responsibility?

1

CMAR (Construction Manager at Risk)

2

DBB (Design-Bid-Build)

3

DB (Design-Build)

4

IPD (Integrated Project Delivery)

35

Multiple Choice

You are managing a hospital construction project with strict deadlines and multiple specialized trades. The owner wants more control but prefers not to manage every trade contract directly. Which delivery method would be most appropriate?

1

DBB

2

CMMP (Construction Management Multi-Prime)

3

BOT

4

JOC

36

Multiple Choice

A private company has been contracted to finance, build, and operate a highway toll system for 20 years before handing it over to the government. What delivery method best describes this arrangement?

1

BOT (Build-Operate-Transfer)

2

DB (Design-Build)

3

MATOC

4

CMAR

37

media

38

media

39

Multiple Choice

Which bidding strategy is most appropriate when maximum competition is desired, typically in the public sector?

1

Selective Bidding

2

Open Bidding

3

Negotiated Bidding

4

Double-Stage Bidding

40

Multiple Choice

Your organization is planning a complex infrastructure project and prefers to work with a trusted vendor who understands the technical requirements. Which bidding method should you use?

1

Open

2

Selective

3

Negotiated

4

Framework

41

media

42

media

43

media

44

media

45

media

46

Multiple Choice

You are evaluating two contractors. One has the lowest bid but a history of poor safety incidents. The other has a slightly higher bid but an excellent safety record and strong financials. Based on evaluation best practices, what should you consider?

1

Award the contract to the lowest bidder to save costs

2

Select the contractor with the better safety and financial record

3

Reopen the bidding process

4

Choose whichever contractor has better marketing material

47

media

48

media

49

media

50

Multiple Choice

Which contract type is most suitable for a construction project with a clearly defined scope and deliverables?

1

Cost Plus Fee

2

Time & Material (T&M)

3

Fixed-Price (Lump Sum)

4

Unit Rate Contract

51

Multiple Choice

You're managing a project with evolving requirements, and the scope is still not finalized. Which contract type would be most appropriate to protect the contractor from undefined risks?

1

Fixed-Price (Lump Sum)

2

Time & Material (T&M)

3

Cost Plus Fee

4

Incentive-Based Contract

52

Multiple Choice

A government agency is hiring a contractor to complete minor, recurring maintenance work, but the scope varies from month to month. The agency prefers flexibility and tracking costs as they occur. Which contract type is most appropriate?

1

Fixed-Price (Lump Sum)

2

Time & Material (T&M)

3

Cost Plus Fee

4

EPC Turnkey

53

media

54

media

55

media

56

media

57

media

58

Multiple Choice

Which of the following best describes a "claim" in construction contract management?

1

A legal dispute requiring litigation

2

A request for additional time, money, or compensation due to unmet obligations

3

A scheduled payment milestone

4

59

Multiple Choice

A subcontractor submits a request for extra payment due to scope changes, but the main contractor rejects it. What is this situation now considered?

1

Variation

2

Conflict

3

Dispute

4

Arbitration

60

Multiple Choice

A project manager prefers a quick, informal method to resolve a conflict without involving legal procedures. Which method is most suitable?

1

Mediation

2

Litigation

3

Arbitration

4

Negotiation

61

media

62

media

63

64

media

65

media

66

media

67

media

68

media

69

Multiple Choice

You are managing a project that involves multiple subcontractors and tight deadlines. What should be your first step in managing risks?

1

Identify and assess potential risks early

2

Wait until a problem arises

3

Monitor only financial transactions

4

Fire high-risk contractors

70

Multiple Choice

Sudden political instability halts your construction project, and this risk was never considered. How should this be classified?

1

Known-known

2

Known-unknown

3

Unknown-unknown

4

71

Multiple Choice

Your team identifies that "staff leave in summer" might affect the schedule. What action should you take?

1

Ignore it since it's seasonal

2

Add it to the risk register and define a response

3

Replace the staff

4

Add penalties for absence

72

media

73

media

74

media

75

Multiple Choice

Which of the following correctly represents the sequence of steps in the risk management process?

1

Identify, Prioritize, Monitor, Analyze, Implement

2

Identify, Analyze, Prioritize, Plan Responses, Monitor

3

Plan Responses, Identify, Analyze, Monitor, Prioritize

4

Analyze, Identify, Monitor, Plan, Prioritize

76

Multiple Choice

During which step of the risk management process are risks ranked using tools like a risk matrix?

1

Identify Risks

2

Analyze Risks

3

Prioritize Risks

4

Monitor Risks

77

Multiple Choice

As a construction project manager, you’ve identified potential delays from late equipment deliveries. You’ve assessed the impact and likelihood. What should your next step be?

1

Ignore the risk unless it happens

2

Rank the risk to decide how urgent it is to address

3

Escalate the issue to the finance team

4

Close the risk register

78

media

79

media

80

media

81

Multiple Choice

A construction project faces potential weather delays next month. What should the project manager do?

1

Document it in the issue log and resolve it

2

Document it in the risk register and plan a mitigation strategy

3

Ignore it unless it happens

4

Immediately escalate it to senior management

82

media

83

media

84

Multiple Choice

During a project review meeting, a contractor raises concerns about recent budget fluctuations and late supplier payments. What category of risk is being discussed?

1

Operational

2

Financial

3

Environmental

4

Project-related

85

media

86

media

87

Multiple Choice

What is the correct formula for calculating a Risk Score in construction risk assessment?

1

Probability ÷ Impact

2

Impact × Probability

3

Probability + Impact

4

Impact − Probability

88

Multiple Choice

A construction manager assesses a risk with a probability of 3 (Probable) and an impact rated as 2 (Serious). Based on the risk matrix shown, how should this risk be classified?

1

Low

2

Medium

3

Critical

4

High

89

Multiple Choice

Which of the following combinations would result in a Low risk rating on the matrix?

1

Probable + Fatal

2

Unlikely + Minor

3

Possible + Serious

4

Probable + Serious

90

media

91

media

92

Multiple Choice

Which of the following is not a valid risk response strategy for threats (negative risks)?

1

Avoid

2

Mitigate

3

Share

4

Transfer

93

Multiple Choice

Your project faces a high-impact risk that your team is not equipped to manage. You decide to purchase insurance to cover any potential losses. Which response strategy are you using?

1

Avoid

2

Accept

3

Escalate

4

Transfer

94

Multiple Choice

You identify an opportunity to significantly increase profits by collaborating with another firm that has access to new markets. Which risk response strategy is best?

1

Accept

2

Share

3

Escalate

4

Enhance

95

media

96

media

97

media

98

media

99

media
media

Show answer

Auto Play

Slide 1 / 99

SLIDE