Planning and overseeing PTT 2
Presentation
•
Construction
•
Vocational training
•
Practice Problem
•
Hard
Donna Hollett
FREE Resource
38 Slides • 29 Questions
1
2
Multiple Choice
What is the main focus of Unit 105?
Understanding electrical work activities
Planning electrical work
Overseeing electrical work activities
Organising work programmes
3
4
Multiple Choice
What are the factors that influence work completion time in electrical work activities?
Cost of materials
Expected hours
Profit margin
Weather conditions
5
6
Multiple Choice
What factors should be considered before work can begin?
Availability of skilled workers
Weather conditions
Storage areas
All of the above
7
Multiple Choice
Which planning tool is used to allocate resources over a specific period?
Schedules
Standards
Policies
8
Multiple Choice
Which process puts more resources on the critical path?
crashing
fast tracking
leading
shortening
9
10
Multiple Choice
What factors influence the deployment and availability of suitable personnel on a work site?
Too many people on site
Different skills and abilities
Experience of electricians
All of the above
11
12
Multiple Choice
What are the methods to ensure the delivery and availability of equipment, components, and material on site?
Deliveries from your company's store
Mass deliveries to site
Just in time deliveries from a supplier/wholesaler
None of the above
13
14
Multiple Choice
What factors can influence work completion time at construction sites due to weather conditions?
Exposure to elements
Availability of materials
Worker experience
Construction design
15
Multiple Choice
The project duration in a network can be determined by the largest value of which variable associated with the critical path?
Slack Time
Earliest Start Time
Earliest Finish Time
Activity Time
16
Multiple Choice
Which process puts more resources on the critical path?
1. Activity e with preceding activities STart, and duration of 8 days
2. Activity F with preceding activities E and duration of 4 days
3. Activity G with preceding activities E and duration of 10 days
4. Activity H with preceding activities F and G and duration of 2 days
5. Activity I with preceding activities H and duration of 2 days
6. Activity J with preceding activities H and duration of 2 days
7. Activity K with preceding activities H and duration of 3 daus
8. Activity L with preceding activities I, J, and K and duration of 2 days
9. Activity M with preceding activities L and duration of 1 day
19 days
25 days
26 days
27 days
17
Multiple Choice
Which of the following best describes critical path analysis?
It shows how a project can be completed with maximum labour resources
It shows how a project can be completed in the minimum time
It takes account for unforeseen events
It predicts the success of a project
18
Multiple Choice
Which best describes the critical path slack?
the activities on the critical path
the delay after the drywall is completed in a house to allow it to dry
the earliest a new HVAC system can be ordered from a manufacturer
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
19
20
Multiple Choice
What factors should be considered regarding work completion time due to other services?
Delays caused by other services
Internal service delays only
Public service delays only
No consideration needed
21
22
Multiple Choice
What is a variation order and why is it important in construction contracts?
A document detailing changes requested
A type of contract
A plan for extra work
A payment method
23
24
Multiple Choice
What is the consequence of a breach of contract?
Formation of a new contract
Legal remedies
Automatic termination
No consequence
25
26
Multiple Choice
What is the purpose of a Gantt chart in work planning?
To allocate resources
To track expenses
To schedule activities
To measure performance
27
28
Multiple Choice
According to the bar chart, which task takes the longest time to complete?
Install cladding
Windows & main doors
Roof frame
Concrete slab
29
Multiple Choice
What does the histogram represent in terms of the mass of each package?
Number of packages
Average mass
Total mass
Standard deviation
30
31
Multiple Choice
What are the steps involved in installing the floodlighting in a car park?
Dig trenches
Deliver lampposts
Fix lampposts
Inspect and test
32
33
Multiple Choice
What is the total estimated time required to complete all tasks listed in the Gantt chart?
30 hours
28.5 hours
25 hours
20 hours
34
Multiple Choice
In an environment where the planned activities have been accomplished previously, there are several ways of getting time estimates. Which of the following is the least useful?
Learning curve models
Statistical methods
Random Number Generator
Prior Experiences
35
36
Multiple Choice
What is the significance of the start and end dates in a Gantt chart?
They indicate the duration of the project
They show when the team is on holiday
They are used for color coding
They determine the complexity of the project
37
38
Multiple Choice
What are the stages involved in Critical Path Network planning?
Identify the operations and components
Determine the duration of each operation
Form a network that relates the operations in a logical sequence
Calculate the total cost of the project
39
40
Multiple Choice
What is the total number of days required to complete the following tasks: Lay Foundations, Build walls, Fit roof, Electric 1st fix, Electric 2nd fix, Plumbing 1st fix, Plumbing 2nd fix, and Inspect and test?
12 days
14 days
15 days
10 days
41
42
43
44
45
Multiple Choice
What is the critical path in project management?
The shortest path of events
The path that takes the longest time
The path with the least resources
The path with the most tasks
46
47
Multiple Choice
What does the bar chart represent in terms of work progress?
Tasks completed
Tasks pending
Tasks in progress
Tasks not started
48
49
Multiple Choice
What should your management plan include when overseeing work programmes?
Working from plans and specifications
Ignoring health and safety procedures
Not coordinating with other trades
Avoiding conflict resolution
50
51
52
Multiple Choice
What are the sources of technical and functional information provided by manufacturers?
Catalogues
Data sheets
User manuals
Product reviews
53
54
Multiple Choice
What types of information do companies supply to their employees?
Working hours
Health and safety requirements
Pay rates
All of the above
55
56
57
58
59
60
61
62
63
64
65
66
67
Show answer
Auto Play
Slide 1 / 67
SLIDE
Similar Resources on Wayground
65 questions
Copy of G2_K8_L2_22-23
Presentation
•
KG - Professional Dev...
62 questions
Elasticsearch and the Elastic stack
Presentation
•
Professional Development
61 questions
AWS-CCP-W3D2
Presentation
•
Professional Development
63 questions
PHNAVY BMC Lecture 4 - Atmospheric Temperature
Presentation
•
Professional Development
61 questions
Do for emphasis *1
Presentation
•
Professional Development
63 questions
Hardware & Diagnostics - Components Lesson
Presentation
•
Professional Development
60 questions
UI Training Module 1 - Intro to Unemployment Insurance
Presentation
•
Professional Development
61 questions
LIGHT
Presentation
•
KG
Popular Resources on Wayground
10 questions
Safety Day 2026 – Student Review
Quiz
•
9th Grade
21 questions
Continents and Oceans
Quiz
•
6th Grade
20 questions
Parts of Speech
Quiz
•
5th Grade
16 questions
Subject & Predicate
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
12 questions
Map Skills
Quiz
•
3rd Grade
22 questions
Continents and Oceans
Quiz
•
5th Grade
15 questions
Rounding Decimals
Quiz
•
5th Grade