Task 6 Setting out

Task 6 Setting out

Assessment

Presentation

•

Construction

•

Vocational training

•

Practice Problem

•

Medium

Created by

Colin Barron

Used 1+ times

FREE Resource

18 Slides • 15 Questions

1

media

2

media

3

Open Ended

How might the ability to measure angles with a protractor be useful in real-world applications beyond drawing?

4

media

5

Multiple Choice

Which of the following is NOT typically included as an underground service?

1

Water pipe

2

Gas pipe

3

Electrical cable

4

Telephone pole

6

media

7

Open Ended

Explain why site clearance is an important step before construction work begins.

8

media

9

media

10

Fill in the Blank

The building line is established by the ___ and the client.

11

Multiple Select

Which of the following statements about building and frontage lines are correct?

1

The building line is established by the architect and client.

2

No construction can be built over the frontage line.

3

The frontage line represents the back edge of the building plot.

4

The building line is shown on the drawings.

12

media

13

Open Ended

Describe the potential consequences of inaccurate right angle setting during construction.

14

media

15

Multiple Select

Which of the following methods can be used to check that a build is at a right angle?

1

3:4:5 method

2

Builders square

3

Optical square

4

Spirit level

16

media

17

media

18

Multiple Select

Which of the following are essential steps in setting out a basic building?

1

Transferring levels

2

Checking diagonals

3

Removing topsoil

4

Indicating wall and trench positions on profiles

19

Multiple Choice

What is the main reason for removing the topsoil during site clearance before starting construction?

1

It contains a high content of vegetable matter, making it unsuitable for building.

2

It is too hard to dig through.

3

It is required for landscaping.

4

It prevents water drainage.

20

media

21

media

22

Fill in the Blank

The common method used in construction to check if a corner is square is the ___ method.

23

Open Ended

Explain how diagonal measurements are used to ensure a building is square during the setting out process.

24

media

25

media

26

media

27

Multiple Choice

Which of the following is indicated by the centre line in the process of setting out a building foundation?

1

The midpoint of the foundation width

2

The location for marking soil

3

The position of the datum peg

4

The end bearing of a lintel

28

media

29

Open Ended

Explain why coloured spray paint or soft sand is used when marking soil during the setting out of buildings.

30

media

31

Multiple Select

Which of the following steps are necessary to ensure accuracy when transferring levels between pegs?

1

Marking only alternate pegs

2

Reversing both straight edge and level each time

3

Using a datum peg

4

Ensuring lintel is fully bedded on mortar

32

media

33

Fill in the Blank

Ensure lintel is fully bedded on ___ mortar.

media

Show answer