PROCUREMENT
Authored by Dawn Towles-Richards
Other
University
Used 112+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Which of the following methods does not require a licensed architect, engineer, or land surveyor?
Construction Manager
Design-Build
Lease-Purchase
Construction Bid
2.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
A performance bond is required when the project amount exceeds______________.
$15,000
$10,000
$5,000
$25,000
3.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
Capital spending is reserved for supplies, payroll, and maintenance.
True
False
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
The Missouri Prompt Payment Act
makes sure contractors and suppliers are paid in timely manner.
requires payments to contractors at least monthly and within 30 days after completion.
says a school district can retain certain amounts until the district can verify the completion of the project.
All of the above are correct.
5.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
A conflict of interest exists when
a board member has inside information on a bid and earns the contract.
An outside bidder is awarded a contract.
a previous bidder is awarded a contract.
No bid was required for a project.
6.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
Advertising is not required for construction bids under $50,000
True
False
7.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
The procurement process does not require checks and balance.
True
False
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?