Project Time Management

Project Time Management

University

12 Qs

quiz-placeholder

Similar activities

Hands-on Modul 3

Hands-on Modul 3

University

10 Qs

Java Quiz 4

Java Quiz 4

University

15 Qs

HCI Week 3

HCI Week 3

University

10 Qs

Visual Basic 2010

Visual Basic 2010

8th Grade - University

10 Qs

CBA Excel 1

CBA Excel 1

University

10 Qs

Binary Tree

Binary Tree

University

14 Qs

Linked List 2

Linked List 2

University

10 Qs

Web Development Revision 1

Web Development Revision 1

University

15 Qs

Project Time Management

Project Time Management

Assessment

Quiz

Computers

University

Hard

Created by

SALIMAH MoKhTaR

Used 121+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

In which of the following project phases is the project schedule developed?
Conceptual
Planning
Implementation
Design

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

To crash a schedule you should:
Increase the time allowed on those tasks that have float.
Try to invest more time on tasks that are behind schedule
Replace the team members that are not performing well
Put extra resources on the tasks that are on critical path.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Completion of the successor activity depends upon the completion of its predecessor activity.
start-to-start
start-to-finish
finish-to-start
finish-to-finish

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The inputs used in the Define Activities process includes all BUT 
Scope baseline
Milestone List
EEF
OPA

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The successful project managers spend most of their time:
Planning with their personnel
Planning with the top management
Communication with the project team
Studying project results

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the output of the Plan Schedule Management process?
Activity list
Schedule Management Plan
Milestone list
Project Schedule Network Diagram

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Free float can be determined
any time after activity durations have been estimated
once the total float for a network path has been calculated
as soon as all activities are defined
none of these

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?