PROJECT RISK MANAGEMENT REV. 2019

Quiz
•
Professional Development
•
Professional Development
•
Hard
Used 28+ times
FREE Resource
Student preview

20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
176. The Key processes of Project Risk Management are:
Plan Risk Management, Identify Risks, Assess Risks, Mitigate Risks,Transfer Risks, and Document Outcomes.
Identify Risks, Plan Risk Management, Evaluate Risks, Develop Risk Responses,Mitigate Risks, and Document Results.
Identify Risks, Perform Qualitative Risk Validation, Perform Quantitative Impact Assessment, Develop Risk Response Strategies,Document Response Strategies, and Monitor Risk Responses.
Plan Risk Management, ldentify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses, Implement Risk Responses,and Monitor Risks.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
177. Strategies typically used to deal with threats or risks that may have negative impacts on project objectives if they occur include all of the following EXCEPT:
Interpreting
Avoiding
Transferring
Mitigating
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
178. Risk transference nearly always involves:
Eliminating risk through beta testing.
Policies and procedures for a response system.
Accepting a lower profit if some activities overrun their budget.
Payment of a risk premium to the party taking on the risk.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
179. In the Plan Risk Responses process, an accept strategy for a negative risk or threat indicates that the project team has decided:
To agree with the project manager.
To eliminate a specific risk or threat, to reduce the probability and / or impact of an adverse risk event to be within acceptable threshold limits, or to pursue an opportunity actively.
Not to change the project management plan to deal with a risk, or it is unable to identify any other suitable response strategy.
To purchase insurance, or to require performance bonds, warranties, and guarantees.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
180. The primary output of the Identify Risks process is the:
Risk register.
Expected monetary value of the risk events.
List of corrective actions.
Risk mitigation plan.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
182. All of the following are inputs to the Identify Risks process EXCEPT:
Risk management plan.
Scope baseline.
Risk mitigation plan.
Quality management plan.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
183. Outputs from the Plan Risk Responses process include all of the following EXCEPT:
Change requests.
Corrective actions.
Project documents updates.
Project management plan updates.
Create a free account and access millions of resources
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade