196. All of the following are inputs to the Plan Procurement Management process, EXCEPT:
Risk register.
Stakeholder register.
Procurement strategy.
Enterprise environmental factors.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
197. Generally, a bid differs from a proposal in that the term:
Bid is used when the seller selection decision will be based on price.
Bid is used when technical capability or technical approach are paramount.
Proposal is used when the selection decision will be based on price.
Proposal is used when the project time frame is limited.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
198. The buyer structures procurement documents, which include all of the following EXCEPT:
Procurement statement of work.
Bid documents
Source selection criteria and independent cost estimates.
Control procurement documents.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
199. Approved change requests can generally include all of the following EXCEPT:
Modifications to the terms and conditions of the contract.
Modification to pricing.
Seller invoices.
Modification to descriptions of the products, services, or results to be provided.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
200. Which of the following is FALSE about advertising as one of the tools and techniques of the Conduct Procurement's process?
Some government jurisdictions require public advertising of certain types of procurement items.
Advertisements in general circulation publications and using online resources can cause public pressure, resulting in bid disputes.
Advertising can often be used to expand existing lists of potential sellers.
Advertisements can be placed in general circulation publications such as selected newspapers or in specialty trade publications.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
201. The buyer, usually through its authorized procurement administrator, provides the seller with ______________as an output of the Control Procurement process.
Formal written notice that the contract has been completed
Letters of commendation to all project team members
Informal notice of acceptance of the deliverables
A copy of the internal notice of completion provided to senior management
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
202. In which type of contracts do buyers need to precisely specify the product or services being procured?
Cost plus award fee contracts.
Fixed-price contracts.
Cost-reimbursable contracts.
Partnership contracts
Create a free account and access millions of resources
Popular Resources on Wayground
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
20 questions
PBIS-HGMS

Quiz
•
6th - 8th Grade
10 questions
"LAST STOP ON MARKET STREET" Vocabulary Quiz

Quiz
•
3rd Grade
19 questions
Fractions to Decimals and Decimals to Fractions

Quiz
•
6th Grade
16 questions
Logic and Venn Diagrams

Quiz
•
12th Grade
15 questions
Compare and Order Decimals

Quiz
•
4th - 5th Grade
20 questions
Simplifying Fractions

Quiz
•
6th Grade
20 questions
Multiplication facts 1-12

Quiz
•
2nd - 3rd Grade