TOG - PMP Quiz 3
Professional Development
Professional Development
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
25 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Managing stakeholder engagement:
is a planning activity
uses risk management plan as an input
occurs at the end of the project
occurs throughout the project life cycle
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The customer calls you to ask about the status of the project, and you have an answer prepared as you are speaking with them. This is an example of:
Meeting customer expectations.
A project manager is always proactive
Always keeping a stakeholder with high interest and high influence satisfied.
Acquiring validation.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager holds the first risk meeting of the project team. The client is present at the meeting. At the meeting several risks are identified and assigned to members of the project team for evaluation and quantification. The result of the meeting is:
Expected value of the risk events.
Strategies for the risk events.
A list of potential risk events.
General statements about risks for the project.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used?
Critical path method
Three-Point Estimate
Monte Carlo
Resource leveling
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 20, and a late finish (LF) of day 30. The activity:
is on the critical path.
has a lag.
has a lead.
is not on the critical path.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Conflict resolution techniques that may be used on a project include confronting, smoothing, forcing and:
withdrawing.
directing.
organizing.
controlling.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which phase of the project is likely to have the greatest amount of its funding spent?
Initiating
Executing
Planning
Closeout
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?