Pre-Test Procurement Management

Quiz
•
Professional Development
•
Professional Development
•
Medium
PMP NOKIA
Used 54+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
In order to procure required materials for a project, your team prepares documents that will be used to solicit information, quotations, and proposals from prospective sellers. The documents are structured to facilitate an accurate and complete response from each prospective seller and to facilitate the evaluation of the responses.
What type of documents is your team creating?
Vendor documents
Source selection criteria
Bid documents
Test and evaluation documents
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is an input to the Plan Procurement Management process?
Procurement management plan
Procurement strategy
Project charter
Stakeholder management strategy
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have completed a nine-month project, and you are in the closing stage. The project completed on time and under budget and everyone in you department has congratulated you on your achievement. The vice president of your company heard about the success of your project and wants a summary overview of project performance so that he can talk about your success at the next board meeting.
What should you provide to him?
Lessons learned repository
Project closure documents
Final lessons learned register
Final report
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Two qualified vendors have been identified for a project. The requesting organization is capable of performing the work, but it was deemed less cost-effective to do so. During vendor selection, the project manager learns that one vendor already works with a competitor and are restricted by an exclusivity clause, The other vendor is not available during the required time frame.
What might the project manager have done differently to avoid this situation?
Include the evaluation method in the procurement documents
Obtained an independent cost estimate
Tailored the way the procurement processes were applied
Conducted a make-or-buy analysis
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Where would you look to find what activities should be performed to close out contracts on your project?
Enterprise environmental factors
Resource management plan
Project management plan
Procurement documentation
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Services are still being billed to the project even though the project manager believes no additional services are required or requested.
What is the best course of action for the project manager to take?
Confirm that no more services are needed and the procurement agreements are closed
Close all agreements with all service providers engaged with the project
Forward the service bills to the project management office for further review and approval
Continue paying the bills until the project is formally closed to avoid claims
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are leading a project with some of the deliverables outsourced to a vendor. You have been working closely with your procurement administrator to ensure hat all claims, invoices, and final payments have bee finalized with the vendor. Terms and conditions of the contract have been met, and all deliverables have been accepted.
What should you do next?
Notify the vendor that the contract has been completed
Finalize all activities for the project and release the project team
Conduct the final inspection of the vendor’s deliverables
Carry out a structured review of the procurement process
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
PURCHASING MANAGEMENT - PURCHASING - JUN23

Quiz
•
Professional Development
23 questions
Pre-Study: Subcontracting in GSI

Quiz
•
Professional Development
15 questions
Kuis 1 Project Administration

Quiz
•
Professional Development
17 questions
Accounts receivable

Quiz
•
Professional Development
20 questions
POST TEST Pelatihan E-Procurement

Quiz
•
Professional Development
15 questions
All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Quiz
•
Professional Development
20 questions
PMP Procurement Exercise

Quiz
•
Professional Development
20 questions
Quiziz Week 3 Day 2

Quiz
•
Professional Development
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade