1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Must the Product Owner be present at the Sprint Retrospective?
It is optional. Attendance is only required when the Product Owner gets invited by the Scrum Master.
It is mandatory. The Sprint Retrospective is an opportunity for the Scrum Team to assess its performance and improve itself.
It is not allowed. The Sprint Retrospective is an opportunity for the Development Team to inspect itself.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When can the Product Backlog be updated?
Only after a Sprint Review if agreed to by the stakeholders
Only during Product Backlog refinement sessions if the Product Owner is present
Never, unless agreed to by the change request
At any time when done by the Product Owner or at the Product Owner's discretion
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How can a Product Owner use time-boxed Sprints to obtain feedback from users and the market?
Through the assurance that a Development Team finishes all work on the Sprint Backlog.
Through frequent delivery of Increments of the product into the market.
By making sure a Sprint does not stop until all testing is done, and the work is verified by the Product Owner.
At the end of each Sprint, a detailed report with all test cases and test results is available.
A business analyst represents the Product Owner to make decisions on his behalf during the Sprint. This way the Product Owner can accept the work at the Sprint Review without further involvement.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A first Sprint can start before the Product Owner has a complete and exhaustive Product Backlog in place.
True
False
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The value delivered by a product can only be determined by revenue.
True
False
6.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What two things best help the Product Owner manage the value of a product?
Setting value on individual Product Backlog items using Value Poker
Devising a formula for a neutral calculation of value
The order of the Product Backlog
Validating assumptions of value through frequent releases
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The Product Owner manages the Product Backlog. Who is accountable for estimating the effort to complete the Product Backlog items?
The Development Team. As a collective, they have a complete view of the work needed to transform Product Backlog items into Increments of product.
The PMO. They have all the history on projects delivered, and this enables the IT department to make delivery commitments.
The Product Owner. The Product Owner is required to commit on delivery to the users and the stakeholders.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?