15 - Critical Path Analysis & Gantt Charts

Authored by Laura Sherrington

Computers, Business

12th Grade

Used 115+ times

15 - Critical Path Analysis & Gantt Charts
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Identify the longest task?

Fill Kettle

Boil Kettle

Put tea in cup

Put sugar in cup

Get milk out of fridge

2.

FILL IN THE BLANKS QUESTION

1 min • 1 pt

Media Image

How many milestones are there?

(a)  

3.

FILL IN THE BLANKS QUESTION

1 min • 1 pt

Media Image

How many tasks are dependent on pouring water into a cup?

(a)  

4.

FILL IN THE BLANKS QUESTION

1 min • 1 pt

Media Image

How many seconds form the critical path?

(a)  

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Critical Path Analysis

A project management technique for process planning that defines critical (milestones) and non-critical tasks

A graphical display of project activities represented by an area of land showing physical features

A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site

A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does PERT stand for?

Project Evaluation and Review Technique

Programme Estimate and Reward Time

Process End and Replace Technique

Programmer Expire and Revised Timescale

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What type of diagram is this?

PERT

Dataflow diagram

Bar Chart

Gantt Chart

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?