1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Samuel is developing a document that will outline the methods used to create and manage requirements, as well as the methods used to prioritize requirements. Samuel is preparing the:
requirements documentation
requirements management plan
requirements traceability matrix
work breakdown structure
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Sebastian is working on a project to make a new sports backpack. He is working with his stakeholders to decide on the color combination for the backpack. Sebastian decides that they will vote, and everyone has to agree on the color combination. What method of group decision making is he using?
unanimity
majority
plurality
dictatorship
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Carl is working on a new phone design for a technology company. He is
currently working on a way to analyze, document, and manage all the
stakeholder requirements for the new design. Kacie is working on the:
requirements management plan.
requirements documentation.
requirements traceability matrix.
work breakdown structure.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Cathy is managing a project and is considering relocating
her team closer to the project worksite. She asks the
stakeholders to vote on this decision and will make the move only if
they all agree to it. Cathy is using which tool /technique to collect
requirements?
dictatorship
plurality
unanimity
majority
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Charley is a event planner and is considering locations for a corporate party. She has decided to ask the all of the stakeholders to vote on two locations, so that whichever location receives over 50% of the group's
support will win. Charley is using which technique to collect requirements?
unanimity
dictatorship
plurality
majority
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Perry is in charge of planning a charity event for the animal shelter. He wants
to review the requirements of each of the stakeholders. Perry should be
reviewing which document?
requirements management plan
requirements documentation
requirements traceability matrix
work breakdown structure
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Adam is leading a rental project. He meets with the stakeholders
to define and document all the needs for the rental project. The
activity that Adam is participating in is referred to as:
verifying scope
creating the WBS
controlling the scope
collecting requirements
Create a free account and access millions of resources
Similar Resources on Wayground
12 questions
Mgmt. Strand 4. Business Governance (A)

Quiz
•
9th Grade - University
10 questions
24-25 Basics of Delphi

Quiz
•
9th - 12th Grade
10 questions
Ethics & Social Responsibility

Quiz
•
10th - 12th Grade
15 questions
Operations Management

Quiz
•
11th - 12th Grade
8 questions
U6 LOC: HR (Production) + Labour Market Analysis quiz 1

Quiz
•
12th Grade
11 questions
SDLC1

Quiz
•
12th Grade
10 questions
Sole Traders, Partnerships and Franchises

Quiz
•
9th Grade - University
12 questions
Fixed and working capital

Quiz
•
12th Grade
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade