Unit 4 Project Management

Unit 4 Project Management

9th - 12th Grade

35 Qs

quiz-placeholder

Similar activities

PMI Mock Follow Up 2 23

PMI Mock Follow Up 2 23

10th Grade

30 Qs

Advanced Accounting Chapter  4 Review

Advanced Accounting Chapter 4 Review

10th - 12th Grade

37 Qs

PMI:Project Charter &  Stakeholders Quiz

PMI:Project Charter & Stakeholders Quiz

12th Grade

30 Qs

Management Module Review

Management Module Review

9th - 12th Grade

31 Qs

Bus Tech Chapter 14

Bus Tech Chapter 14

9th - 12th Grade

38 Qs

F24 - Managing HR and Labor Relations

F24 - Managing HR and Labor Relations

10th Grade

31 Qs

UNIT 1 AND 2 STUDY GUIDE PART 1

UNIT 1 AND 2 STUDY GUIDE PART 1

12th Grade

33 Qs

Unit 4 Project Management

Unit 4 Project Management

Assessment

Quiz

Business

9th - 12th Grade

Hard

Created by

albert reid

Used 46+ times

FREE Resource

35 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Due to a gasoline shortage, Ann is unable to secure the gasoline needed to fill up her tractor prior to planting. This is an example of a/an:

abstract dependency.

discretionary dependency.

external dependency.

mandatory dependency.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Ashlyn's pottery project for art class must dry before she can put on a final coat of glaze. This is an example of a/an:

abstract dependency.

discretionary dependency.

external dependency.

mandatory dependency.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which best describes the critical path slack?

the activities on the critical path

the delay after the drywall is completed in a house to allow it to dry

the earliest a new HVAC system can be ordered from a manufacturer

the earliest a new HVAC system can be ordered from a manufacturer without delaying the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Alex prefers to complete the plumbing work in his construction projects before completing electrical work. This is an example of a/an:

mandatory dependency.

discretionary dependency.

external dependency.

abstract dependency.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Andy prefers to set up furniture before hanging window treatments for his interior design projects. This is an example of a/an:

abstract dependency.

discretionary dependency.

external dependency.

mandatory dependency.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Alex orders all of the plumbing supplies for his construction projects from the same vendor. Due to a recent fire, the vendor is unable to deliver the supplies when needed. This is an example of a/an:

mandatory dependency.

discretionary dependency.

external dependency.

abstract dependency.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Craig needs to weld the car chassis together before Jim can install the engine. This represents a/an:

abstract dependency.

discretionary dependency.

external dependency.

mandatory dependency.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?