1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be done to the foundation before installing the sill plates?
Square / 3-4-5 the foundation
It is insulated
Place nuts on the anchor bolts
Joist are installed
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Framing the first deck before backfilling the foundation helps provide___________.
Level
Plumb
Square
Lateral support
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Before the sill plate nuts are tightened down, make sure they are _________.
On Center
Plumb
Crowned
Level
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Tools that can be used to level the sill plates are a 8 foot level and/or a ____________.
Plumb bob
Builder's level
Torpedo level
Framing square
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What parts make up the rim joist?
Tail joists and trimmers
Header joist and end joists
Cantilevered joists
Sill plates and girders
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What type of nails should be used to nail the rim joist and how often should they be placed?
8d 6"OC
8d 12" OC
16d 6" OC
16d 12" OC
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If a girder must be more than one piece, where should the joint between the pieces be?
Between support columns
16" OC
It does not matter
Directly over a support column
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?