Project Management Chapter 5

Authored by lucas mak

Business

University - Professional Development

Used 9+ times

Project Management Chapter 5
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The process of forecasting of approximating the time and cost of completing project deliverables is called

Budgeting

Predicting

Estimating

Planning

Guesstimating

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In practice, estimating processeses are frequently classified as

Top down / bottom up

Rough/polished

Precise/order of magnitude

Draft/final

Broad/specific

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the relationship between organizational culture and estimating

There is no relationship

Cultural norms affect the accuracy of estimates

Culture determines whether estimates are made

Estimating alters cultural norms

Estimating and culture are independent

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A good starting point for developing time and cost estimates is

Past experience

Work packages

Task analysis

Time and motion studies

Work breakdown structure

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT one of the factors that need to be considered to improve quality of estimates for project times and costs?

Planning horizon

People

Padding estimates

Profit

Project structure

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing?

Padding estimates

Project duration

Project structure

People

Organization culture

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Companies are using which of the following for improving the estimating process for future projects?

Adjusting estimates based on individual forecasting abilities

Bench marking and using the experience of other companies

Using time and motion studies

Creating historical database of previous projects

Establishing an estimating training course for all employees

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?