30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first value in the Agile Manifesto?

A. Contract Negotiations over Working Plans

B. Working Software over Comprehensive Documentation

C. Individuals and Interactions over Processes and Tools

D. Comprehensive Documentation over Customer Interaction

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the difference between Waterfall/predictive project management and Agile frameworks?

A. Waterfall is preplanned and so are Agile projects.

B. Agile plans are just in time, and Waterfall projects are preplanned.

C. Scope is fixed on Agile projects but not on Waterfall projects.

D. They both are project management frameworks.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In waterfall, the project team often gets early feedback from customers or markets about the product they are building, so they can act on this feedback on time.

A. True

B. False

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When was the agile manifesto written?

A. 2010

B.2015

C.1991

D.2001

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Empirical process control has three main aspects to it. What would those three be?

A. Transparency, inspection, and adaptation

B. Iterative, incremental, and uncertainty

C. Transparency, iterative, reliability

D. Inspection, incremental, adaptable

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are working to implement Agile in your organization, and a key stakeholder asks you to explain Agile to them. What would be the best answer to explain Agile to someone who doesn’t know anything about it?

A. Agile is a way to produce software without change control.

B. Agile is a framework for better project management.

C. Agile is a mindset that allows an organization to focus on better ways to produce value for the customer and practice continuous improvement.

D. Agile is the opposite of Waterfall.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Bill is a key stakeholder in your organization and has recently learned about your usage of an Agile framework on your current project. You’ve invited Bill to a planning meeting, and he says, “I thought you didn’t do formal planning in Agile.” How should you respond?

A. “We do plan our projects, but we keep our focus on the immediate items and we value working software over comprehensive documentation during planning.”

B. “We plan as much as anyone working on projects and try to incorporate the opinions of many stakeholders to help us do it.”

C. “We don’t plan normally, but since you are new to Agile we thought we would plan as much as possible until you get comfortable with Agile.”

D. “We build plans that we know won’t work to meet stakeholder requirements.”

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?