
UAS Project Management

Quiz
•
Other
•
University
•
Medium
Rina Indrayani
Used 108+ times
FREE Resource
50 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity?
Start-to-Start (SS)
Start-to-finish (SF)
Finish-to-Start (FS)
Finish-to-Finish (FF)
2.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Which of the following is NOT a tool or technique used in Estimate Activity Durations?
SWAG Estimation
Parametric Estimation
Analogous Estimation
Three-Point Estimation
3.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Start-A-B-C-Finish
Start-A-D-E-F-Finish
Start-G-H-I-J-Finish
Start-A-B-J-Finish
4.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they’re all assigned to other work. So she is constanly having to go over his head to overrule him. Which type of organixation is she working for ?
Functional
Strong Matrix
Weak Matrix
Projectized
5.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
What’s the correct order og the time management planning processes?
Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule
Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, Estimate Activity Durations
Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule
Develop Schedule, Define Activities, Sequence Activities, , Estimate Activity Resources, Estimate Activity Durations
6.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
You’re working on a project that has an EV of $7362 and a PV (BCWS) of $8232 what’s your SV?
-$870
$870
0.89
Not enough information to tell
7.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Given this portion of the notwork diagram to the right, what’s the ES of activity F?
9
10
12
13
Create a free account and access millions of resources
Similar Resources on Wayground
50 questions
Training Quiz

Quiz
•
12th Grade - University
50 questions
DCET PMS 1-50

Quiz
•
University
50 questions
FINMAN CHAPTER 1 REVIEWER (Theories and Solving)

Quiz
•
University
55 questions
Midterm Revision

Quiz
•
University
50 questions
National 5 Bus Mgt Operations

Quiz
•
KG - University
47 questions
AJP Vidyalankar Polytechnic CHP 5 Part 1

Quiz
•
University
50 questions
Research Questions and Theoretical Framework Development Week 5-

Quiz
•
University
55 questions
Health and safety

Quiz
•
University
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade