You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity?

UAS Project Management

Quiz
•
Other
•
University
•
Medium
Rina Indrayani
Used 108+ times
FREE Resource
50 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Start-to-Start (SS)
Start-to-finish (SF)
Finish-to-Start (FS)
Finish-to-Finish (FF)
2.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Which of the following is NOT a tool or technique used in Estimate Activity Durations?
SWAG Estimation
Parametric Estimation
Analogous Estimation
Three-Point Estimation
3.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Start-A-B-C-Finish
Start-A-D-E-F-Finish
Start-G-H-I-J-Finish
Start-A-B-J-Finish
4.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they’re all assigned to other work. So she is constanly having to go over his head to overrule him. Which type of organixation is she working for ?
Functional
Strong Matrix
Weak Matrix
Projectized
5.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
What’s the correct order og the time management planning processes?
Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule
Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, Estimate Activity Durations
Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule
Develop Schedule, Define Activities, Sequence Activities, , Estimate Activity Resources, Estimate Activity Durations
6.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
You’re working on a project that has an EV of $7362 and a PV (BCWS) of $8232 what’s your SV?
-$870
$870
0.89
Not enough information to tell
7.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Given this portion of the notwork diagram to the right, what’s the ES of activity F?
9
10
12
13
Create a free account and access millions of resources
Similar Resources on Quizizz
45 questions
Midterm Examination in Macro Perspective

Quiz
•
University
47 questions
AJP Vidyalankar Polytechnic CHP 5 Part 1

Quiz
•
University
50 questions
DCET PMS 1-50

Quiz
•
University
55 questions
Midterm Revision

Quiz
•
University
50 questions
W!SE REVIEW

Quiz
•
KG - University
50 questions
Project management 1

Quiz
•
University
50 questions
National 5 Bus Mgt Operations

Quiz
•
KG - University
45 questions
HECATMA Final Quiz

Quiz
•
University
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade