You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity?
Start-to-Start (SS)
Start-to-finish (SF)
Finish-to-Start (FS)
Finish-to-Finish (FF)
2.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Which of the following is NOT a tool or technique used in Estimate Activity Durations?
SWAG Estimation
Parametric Estimation
Analogous Estimation
Three-Point Estimation
3.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Start-A-B-C-Finish
Start-A-D-E-F-Finish
Start-G-H-I-J-Finish
Start-A-B-J-Finish
4.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they’re all assigned to other work. So she is constanly having to go over his head to overrule him. Which type of organixation is she working for ?
Functional
Strong Matrix
Weak Matrix
Projectized
5.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
What’s the correct order og the time management planning processes?
Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule
Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, Estimate Activity Durations
Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule
Develop Schedule, Define Activities, Sequence Activities, , Estimate Activity Resources, Estimate Activity Durations
6.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
You’re working on a project that has an EV of $7362 and a PV (BCWS) of $8232 what’s your SV?
-$870
$870
0.89
Not enough information to tell
7.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
Given this portion of the notwork diagram to the right, what’s the ES of activity F?
9
10
12
13
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?