UAS Project Management

UAS Project Management

University

50 Qs

quiz-placeholder

Similar activities

Boiler and Steam Turbine

Boiler and Steam Turbine

University

46 Qs

VICTOR SAM MEMORIAL QUIZ COMPETITION 2024

VICTOR SAM MEMORIAL QUIZ COMPETITION 2024

University

50 Qs

HMPE11 MIDTERM EXAM

HMPE11 MIDTERM EXAM

University

45 Qs

Module I: Understanding Operating Systems

Module I: Understanding Operating Systems

12th Grade - University

45 Qs

UAS STATISTIK DESKRIPTIF DAN INFERENSIAL

UAS STATISTIK DESKRIPTIF DAN INFERENSIAL

University

50 Qs

CERDAS CERMAT HUT RI 76

CERDAS CERMAT HUT RI 76

1st Grade - Professional Development

45 Qs

Kế Kiểm Học gì? Làm gì?

Kế Kiểm Học gì? Làm gì?

University

45 Qs

FINAL EXAM: LIVING IN THE IT ERA

FINAL EXAM: LIVING IN THE IT ERA

University

50 Qs

UAS Project Management

UAS Project Management

Assessment

Quiz

Other

University

Practice Problem

Medium

Created by

Rina Indrayani

Used 108+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity?

Start-to-Start (SS)

Start-to-finish (SF)

Finish-to-Start (FS)

Finish-to-Finish (FF)

2.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

Which of the following is NOT a tool or technique used in Estimate Activity Durations?

SWAG Estimation

Parametric Estimation

Analogous Estimation

Three-Point Estimation

3.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

Media Image

Start-A-B-C-Finish

Start-A-D-E-F-Finish

Start-G-H-I-J-Finish

Start-A-B-J-Finish

4.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they’re all assigned to other work. So she is constanly having to go over his head to overrule him. Which type of organixation is she working for ?

Functional

Strong Matrix

Weak Matrix

Projectized

5.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

What’s the correct order og the time management planning processes?

Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule

Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, Estimate Activity Durations

Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule

Develop Schedule, Define Activities, Sequence Activities, , Estimate Activity Resources, Estimate Activity Durations

6.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

You’re working on a project that has an EV of $7362 and a PV (BCWS) of $8232 what’s your SV?

-$870

$870

0.89

Not enough information to tell

7.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

Media Image

Given this portion of the notwork diagram to the right, what’s the ES of activity F?

9

10

12

13

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?