PMP PMBOK Module 1-4 Self Assessment

Quiz
•
Other
•
Professional Development
•
Hard
Marleen Cleversey
Used 47+ times
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1- A project manager is working in an organization where project managers have significant authority, and work is defined by a functional manager in the organization. All project managers report to a central manager. What type of organization structure is this?
A.) Functional
B.) Weak matrix
C.) Balanced matrix
D.) Strong matrix
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2- According to the PMBOK® Guide, a project management office (PMO) may manage:
A.) An organization's projects
B.) An organization's projects and facilitates the sharing of resources, methodologies, tools, and techniques
C.) Standardization of project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques
D.) An organization's projects, programs, portfolios, and operations
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3- According to the PMBOK® Guide, who is generally responsible for approving or rejecting complex change requests carried out in major projects at large organizations?
A.) Project customer
B.) Project sponsor
C.) Project manager
D.) Change control board
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4- A scheduling software tool is considered which of the following?
A.) An organizational process asset
B.) An enterprise environmental factor
C.) A configuration management system
D.) A project constraint
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5- An airport employee is a process improvement manager responsible for the overall improvement of the airport’s operations. This employee is currently supervising a number of process improvement projects at the airport relating to passenger experience,immigration, baggage handling, and cargo processes. For every improvement project,there is a project manager reporting directly to this person. Which of the following best describes this role?
A.) Project coordinator
B.) Project manager
C.) Program manager
D.) Portfolio manager
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6- Which of the following is not a part of a project's administrative closure?
A.) Verification of the exit criteria
B.) Auditing project success or failure
C.) Alternative dispute resolution (ADR)
D.) Updating organizational process assets
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7- Which of the following statements is true regarding the Direct and Manage Project Work process?
A.) It is a discrete process that is only performed as part of monitoring & controlling the project.
B.) It is a continuous process that is only performed in parallel with project executing and closing processes.
C.) It is a continuous process that is performed throughout the project.
D.) It is a continuous process that is only performed parallel to the project executing processes.
Create a free account and access millions of resources
Similar Resources on Wayground
30 questions
PM Guild Cup 2023F

Quiz
•
Professional Development
30 questions
Project Management Concepts Quiz_Round 1

Quiz
•
Professional Development
30 questions
Project Management Concepts Quiz_Round 3

Quiz
•
Professional Development
25 questions
HR Quiz for MBA II Year - RGCET

Quiz
•
Professional Development
30 questions
Project Management Fundamentals Quiz_Round 2

Quiz
•
Professional Development
25 questions
Notion Quiz

Quiz
•
Professional Development
25 questions
Business Banking Quiz

Quiz
•
Professional Development
35 questions
Data Migration Cumulative Review Quiz

Quiz
•
Professional Development
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade