1- A project manager is working in an organization where project managers have significant authority, and work is defined by a functional manager in the organization. All project managers report to a central manager. What type of organization structure is this?
PMP PMBOK Module 1-4 Self Assessment

Quiz
•
Other
•
Professional Development
•
Hard
Marleen Cleversey
Used 47+ times
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A.) Functional
B.) Weak matrix
C.) Balanced matrix
D.) Strong matrix
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2- According to the PMBOK® Guide, a project management office (PMO) may manage:
A.) An organization's projects
B.) An organization's projects and facilitates the sharing of resources, methodologies, tools, and techniques
C.) Standardization of project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques
D.) An organization's projects, programs, portfolios, and operations
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3- According to the PMBOK® Guide, who is generally responsible for approving or rejecting complex change requests carried out in major projects at large organizations?
A.) Project customer
B.) Project sponsor
C.) Project manager
D.) Change control board
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4- A scheduling software tool is considered which of the following?
A.) An organizational process asset
B.) An enterprise environmental factor
C.) A configuration management system
D.) A project constraint
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5- An airport employee is a process improvement manager responsible for the overall improvement of the airport’s operations. This employee is currently supervising a number of process improvement projects at the airport relating to passenger experience,immigration, baggage handling, and cargo processes. For every improvement project,there is a project manager reporting directly to this person. Which of the following best describes this role?
A.) Project coordinator
B.) Project manager
C.) Program manager
D.) Portfolio manager
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6- Which of the following is not a part of a project's administrative closure?
A.) Verification of the exit criteria
B.) Auditing project success or failure
C.) Alternative dispute resolution (ADR)
D.) Updating organizational process assets
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7- Which of the following statements is true regarding the Direct and Manage Project Work process?
A.) It is a discrete process that is only performed as part of monitoring & controlling the project.
B.) It is a continuous process that is only performed in parallel with project executing and closing processes.
C.) It is a continuous process that is performed throughout the project.
D.) It is a continuous process that is only performed parallel to the project executing processes.
Create a free account and access millions of resources
Similar Resources on Quizizz
26 questions
Prince2 Agile Capítulos 6-10

Quiz
•
Professional Development
26 questions
CUTE Tutorial

Quiz
•
Professional Development
25 questions
Interviewee Exam for RC District Cooling Plant Project

Quiz
•
Professional Development
25 questions
ISO Refresher

Quiz
•
Professional Development
25 questions
ISO Refresher 2024 CPMTE

Quiz
•
Professional Development
30 questions
Entrepreneurship development MG6071

Quiz
•
Professional Development
30 questions
Atoha PMP lesson 9

Quiz
•
Professional Development
30 questions
Merchant Banking

Quiz
•
University - Professi...
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade