SAFe for teams

SAFe for teams

Professional Development

45 Qs

quiz-placeholder

Similar activities

Exam Pre-intermediate. Grammar / Vocabulary part

Exam Pre-intermediate. Grammar / Vocabulary part

Professional Development

50 Qs

Immunisation Quiz 2022

Immunisation Quiz 2022

Professional Development

50 Qs

Assessment of as for LEARNING

Assessment of as for LEARNING

Professional Development

43 Qs

DPA Game

DPA Game

Professional Development

50 Qs

unit 101/202 rivision

unit 101/202 rivision

Professional Development

40 Qs

Provisioning Type 2 ( Instalasi ODP Closure )

Provisioning Type 2 ( Instalasi ODP Closure )

Professional Development

40 Qs

Famous Landmarks Quiz

Famous Landmarks Quiz

Professional Development

50 Qs

Verbal Ability Quiz-Induction-2022-02

Verbal Ability Quiz-Induction-2022-02

Professional Development

50 Qs

SAFe for teams

SAFe for teams

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Easy

Created by

Frédéric Chenevière

Used 316+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

45 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement is true about work in process (WIP) limits?

Higher WIP limits provide richer feedback
Higher WIP limits result in lower utilization
Lower WIP limits result in fewer Stories being completed
Lower WIP limits improve flow

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why do Lean-Agile leaders try to connect the silos of business, system engineering, hardware, software, test, and quality assurance?

To optimize vertical communication
To align around value
To enforce organizational boundaries between functions
To allow friction between the teams

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the goal of the SAFe House of Lean model?

Innovation
Relentless Improvement
Flow
Value

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement is true about the PI Planning event?

It involves program Portfolio Management to prioritize the Stories presented by teams during the final plan review
It involves everyone in the program over a two-day period
It involves Product Management and Product Owners on the first day and the rest of the teams on the second day
It involves only the team members who are most qualified to estimate the work

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activity is key to successfully implementing the Scaled Agile Framework?

Remove blocks such as portfolio estimation
Replace the PI Planning process with the Inspect and Adapt workshop when possible
Use a cadence-based PI Planning process
Use the Innovation and Planning Iteration instead of the PI Planning process

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the benefit of separating release elements from the Solution?

It allows Agile Teams to launch untested Features
It allows the release of different Solution elements at different times
It allows the Systems Team to integrate with ease
It allows the Agile Release Train to demo value every two weeks

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An Agile Team collects the Iteration Metrics they have agreed upon during which part of the team retrospective?

During the quantitative part of the team retrospective
During the Features agreement retrospective
During the time and materials retrospective
During the qualitative part of the team retrospective

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development