1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Entities, agencies, organizations, and the like that have been accredited/registered with the Board of Architecture of the Professional Regulation Commission to deliver seminars, trainings, lectures, and other Continuing Professional Education Modules for Architects, other than the IAPOA which is automatically accredited by the Board of Architecture.

UAP

CPD Providers

IAPOA

National Convention

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

He is a registered and licensed architect, who is academically and professionally qualified, and with exceptional or recognized expertise or specialization in any branch of architecture.

Architect-of-record

Consulting architect

Architect

Architect-in-charge of construction

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

It was the first law passed by the national assembly in 1921 where the maestros de obra or the master builders are required to register as architects.

Engineers and Architect's Law Act No. 2986

Engineers and Architect's Law Act No. 2896

Engineers and Architect's Law Act No. 9286

Engineers and Architect's Law Act No. 8296

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The architect of a housing project was given Php 300,000.00 for the first unit he designed using the old SPP as reference for professional fees. How much will he receive for the tenth housing unit to be constructed?

Php 60,000.00

Php 120,000.00

Php 180,000.00

Php 240,000.00

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Within how many months shall be the release of retention from date of final payment?

2

3

4

6

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In a PERT CPM, __________ is a starting node to two or more activities.

Concurrent node

Merge node

Simultaneous node

Burst node

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following situation would trigger the owner to suspend work?

Bankruptcy - declared by BIR

Insubordination

Non-payment of contractors debt /

non-superintendence of contractor

All of the above

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?