1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Question 1 of 100Question ID: 612386

A vendor did not perform as contracted, so you are withholding payment as stipulated by the contract. The vendor started using foul language and is calling you names. Your team members are furious, and some of them have responded similarly. Even though you are angry as well, you stay calm and handle the situation with respect.

Which of the following have you demonstrated by responding to the situation in this way?

AConducted yourself in a professional manner

BProved to be loyal to the vendor

CProtected team members from the fight

DBoosted team morale

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Question 2 of 100Question ID: 612386

Who can terminate a contract on a project?

AEither party before the start of work

BThe buyer before the start of work

CEither party by mutual consent

DEarly termination is not an option

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Question 3 of 100Question ID: 612940

The project team has spent a great deal of time reviewing a set of significant changes that a vendor proposed to the specifications of a project deliverable. Everyone eventually agrees that the changes would improve the deliverable without any net effect on the cost.

What should be done next?

AImplement the changes since no additional costs are involved

BIssue a change request to update the procurement management plan

CIssue a change request to update the project management plan

DDeduct the cost of the evaluation process from the vendor's invoice

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Question 4 of 100Question ID: 612379

You have begun evaluating sellers' progress in producing project deliverables to see if there have been any reported issues with quality or availability as well as how the schedule and cost are comparing to the agreement with the vendor.

The activities you are performing can best be described by which of the following?

APlan Procurement Management

BConduct Procurements

CPerformance measurements

DPerformance reviews

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Question 5 of 100Question ID: 651302

A project requires consultant services. How much and for how long these services are needed is not known. The project needs to procure these services quickly.

Which contract type should be used?

ACost plus fixed fee

BTime and material

CCost plus award fee

DFixed fee with economic price adjustments

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Question 6 of 100Question ID: 613708

You as a project manager have outsourced a portion of your work to a vendor with whom neither you nor the sponsor has worked with before. You have a cost-reimbursable contract with the seller. The sponsor, on more than one occasion, has discussed his concerns with you that the seller could easily increase their profits with this type of agreement.

What should you tell the sponsor to decrease his apprehensions?

AYou audit every invoice to ensure the costs are applicable and chargeable to your project.

BYou do not expect any changes to the scope.

CThe seller has the risk with this type of contract.

DWith this type of contract, the seller agrees to a set reimbursement amount, so the final costs to your project are pre-determined.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Question 7 of 100Question ID: 612352

The project manager reviews the issue log at the end of each day. One issue she recorded in the issue log stems from delays in the delivery of material from a contracted supplier. The project manager suspects the procurement process is flawed.

What tool should the project manager use to determine if any adjustments to the procurement process are required?

AInspection

BAudit

CIndependent estimate

DClaims administration

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development