1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 1 of 100Question ID: 651347
To utilize a few employees who are not assigned to any projects this month, the functional manager can authorize a project specifically for them. There are two project ideas that have been vetted. One is an IT project to implement a new software tool. Another is a charity project for the community. Alas, there is only enough budget for one of the projects.
How should the functional manager approach the project chartering?
AEvaluate the business value of each of the projects to determine which one brings more value to the company
BCharter the IT project of the new software tool implementation since it is likely to provide a long-term tangible benefit
CCharter the charity project for the community since it is likely to have a positive, long-lasting, intangible, public benefit
DCharter both projects with a reduced scope that can be covered by the available budget to gain a little value from each
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 2 of 100Question ID: 612030
To develop a charter for the project that you have been assigned to lead, you have reviewed the business documents and studied the agreements. You lack the information about the key project deliverables which should be included in the charter.
What is the best way to obtain this information?
AFacilitate a meeting with key stakeholders
BAsk the project sponsor for their advice
CReview the project scope statement
DTalk to the end users of the projectity since it is likely to have a positive, long-lasting, intangible, public benefit
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 3 of 100Question ID: 626018
A senior manager has just been appointed as a project sponsor for a new project the company is about to undertake. The newly appointed sponsor starts developing a project charter but is not sure what information should be included. The sponsor seeks advice from an experienced project manager.
The project manager responds that at a minimum, the project charter should include which of the following:
AHigh-level information about the project
BDetailed project scope and schedule
CA list of all project stakeholders
DA list of vendors selected for the project
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 4 of 100Question ID: 612065
A project manager was asked to prepare a document, which the project sponsor will sign to authorize a new software development project.
Which of the following will the project manager want to include in this document?
AA work breakdown structure (WBS)
BThe key project deliverables
CA project schedule
DThe project budget
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 5 of 100Question ID: 613012
You are about to hold a kick-off meeting to begin planning for a small project you have been assigned to manage. A stakeholder who has been out of the office for most of the project's initiation phase, asks you for more information about how the project will impact his department.
Which one of the following would be the most appropriate to provide the stakeholder?
AThe project scope statement
BThe approved project charter
CThe project management plan
DThe business case
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 6 of 100Question ID: 613104
A project manager is assigned to a research and development project for an external client and is currently in the process of developing a list of potential stakeholders. The project is still in the initiation stage, and the project charter has yet to be approved. The project manager has already reviewed an early draft of the project charter and consulted the business documents to find potential stakeholders.
What else might the project manager do to identify stakeholders?
ALook at the stakeholder register
BReview the contract
CResearch the business case
DRead the stakeholder engagement plan
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 7 of 100Question ID: 626030
You are reviewing a document that describes the project vision, mission, purpose, objectives, success criteria, high-level requirements, risks, assumptions, the list of key stakeholders, and the name of the assigned project manager.
What else should be specified in this document?
AThe business need and the cost-benefit analysis
BRequirements for formal procurement closure
CDevelopment approach and project life cycle
DMilestone schedule and key deliverables
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
100 questions
Pilihan Ganda
Quiz
•
Professional Development
100 questions
PRETEST PPG 1
Quiz
•
Professional Development
100 questions
National Section Practice Exam - Appendix A
Quiz
•
Professional Development
99 questions
TRCN EXAM practice By Mr Ajibola
Quiz
•
Professional Development
100 questions
D40 MASTER THE DAY
Quiz
•
Professional Development
100 questions
Digital Electronics - MID TERM EXAM
Quiz
•
Professional Development
100 questions
Soal 601-700
Quiz
•
Professional Development
98 questions
NABCEP Study
Quiz
•
Professional Development
Popular Resources on Wayground
20 questions
Halloween Trivia
Quiz
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Order of Operations
Quiz
•
5th Grade
20 questions
Halloween
Quiz
•
5th Grade
16 questions
Halloween
Quiz
•
3rd Grade
12 questions
It's The Great Pumpkin Charlie Brown
Quiz
•
1st - 5th Grade
20 questions
Possessive Nouns
Quiz
•
5th Grade
10 questions
Halloween Traditions and Origins
Interactive video
•
5th - 10th Grade