1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 1 of 100Question ID: 610095
As you execute the quality management plan for a project to develop a new autopilot feature for a vehicle, you have created the diagram below, which compares the vehicle speed with uncommanded lane departures.
What can be said about this diagram?
AAffinity diagram, which shows a weak correlation between the speed and lane departures
BScatter diagram, which shows a strong correlation between the speed and lane departures
CAffinity diagram, which shows a strong correlation between the speed and lane departures
DScatter diagram, which shows a weak correlation between the speed and lane departures
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 2 of 100Question ID: 613219
Four developers have been acquired with a time and materials contract on a software development project. During project execution, the project manager notices that the developers work fewer hours than anticipated, resulting in the project to fall behind schedule. The project manager contracts two more developers, who help bring the project back on track.
What should the project manager do after adding the contractors to the team?
AUpdate the schedule baseline
BInvoke a disciplinary action against the four developers
CPerform individual and team assessments
DRevise the project team assignments documentationion between the speed and lane departures
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 3 of 100Question ID: 613628
The project you are leading will use wood pallets supplied by a vendor. During the testing of the first shipment from the vendor, an engineer discovers 10 of the 100 pallets of wood are subpar and do not meet project specifications.
What should you do immediately?
AWrite an email to the stakeholders explaining the situation
BSchedule a meeting with the team to see if the pallets still can be used
CRecord and document the problem in the project issue log
DCall the vendor and express your dissatisfaction with the delivery
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 4 of 100Question ID: 651408
The project manager is in discussions with vendors about their bids that came in higher than expected. Additionally, according to the vendors' responses, none of them will be able to deliver by the deadline requested. The project manager talks to the sponsor and other key project stakeholders to see if additional funds are needed to cover the extra costs and deliver on schedule.
Which process is the project manager performing?
AControl Costs
BControl Schedule
CAcquire Resources
DConduct Procurements
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 5 of 100Question ID: 612668
A project manager is leading a large project to develop a new model of smartphone. Early in project execution, to foster the stakeholder involvement, the project manager holds a meeting as specified in the stakeholder engagement plan.
What type of meeting does the project manager likely hold?
AA project retrospective to finalize lessons learned register
BA workshop to develop the team charter
CA project kick-off meeting to establish roles and responsibilities of stakeholders
DA meeting to create a comprehensive list of stakeholders
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 6 of 100Question ID: 612263
During product testing, a project team has discovered that some components did not meet government regulations established for the industry. Following the approved change request to repair the defects, the components have been fixed, and the team is ready to test the product again.
What documents should the team refer to while re-testing the product?
AVerified deliverables
BResource requirements
CApproved change requests
DQuality improvement methods
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 7 of 100Question ID: 612593
While executing a project to develop a new computer game, the project manager determines that support for the project is waning among some of the key stakeholders. In order to recapture the stakeholders' initial enthusiasm, the project manager arranges an event for the stakeholders to experience the components of the game that have already been developed. Based on the feedback received, the event was an effective way to keep stakeholders engaged.
What should the project manager do next?
AUpdate the risk register
BRevise the communications management plan
CRecord the information in the lessons learned register
DSubmit a change request to update the lessons learned repository
Create a free account and access millions of resources
Similar Resources on Wayground
99 questions
CLOSING

Quiz
•
Professional Development
102 questions
RiskYMgt01

Quiz
•
Professional Development
99 questions
PMP101-199

Quiz
•
Professional Development
100 questions
M FAHAD USMANI Set-3

Quiz
•
Professional Development
103 questions
CBT-Unit W03- User Interface Design

Quiz
•
Professional Development
100 questions
Moody's Practice Test 2

Quiz
•
Professional Development
100 questions
Subdivision and Housing Regulations

Quiz
•
Professional Development
100 questions
INITIATION

Quiz
•
Professional Development
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade