1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You gave the responsibility of collecting requirement from project stakeholder to four of your team members. After starting the requirement collection process, one of your team members left the job and the requirements could not be compiled properly. Initially, you did not notice this, however, during a product review, a few stakeholders told you that some of the features in the product were not requested by them. Therefore, to verify their comments you review the product requirements and identify the issue.
A. Scope creep
B. Scope slippage
C. Gold plating
D. Opportunity
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During the planning phase, you have created the WBS for the work that you are about to complete. However, because of a lack of information you are not able to create the WBS for the rest of the work, so you leave it until you get the correct and detailed information. This is an example of:
A. Iterative development approach
B. Improper collecting requirement process
C. Rolling wave planning
D. Improper scope statement
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The client informs you that he noticed some parts of the work are not being completed by your team. You ensure him that you will look into it and give a proper response after verifying the facts. Which document will you refer to verify it?
A. Project scope statement
B. WBS dictionary
C. Schedule baseline
D. WBS
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
As the project manager for a large, complex project, you have been getting complaints from your team, including some of the management team, about all the time being spent on planning. You know that by spending time following the appropriate planning process, you can prevent many problems during execution. This will save time in the later stages of the project. One of the primary complaints you were hearing is related to the time it takes to create the Work Breakdown Structure (WBS). You are explaining the importance of the WBS to your project team members. Which of the following statements about the WBS is incorrect?
A.it is a hierarchical decomposition of project work
B. Planned work contained in the lowest level WBS components are called WBS dictionaries.
C. The WBS subdivides the project work into smaller, more manageable pieces of work
D. The WBS organizes and defines the total scope of the project work
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While finalizing the WBS, you assign each work package to a control account and establish a unique identified for the same work from a code of account. These identifiers help you find a hierarchical sum of costs, schedule, etc. Which statement is true about the WBS?
A. It contains all project work
B. It authorizes the project manager
C. It is a hierarchy of project staft
D. It is a hierarchical breakdown of project resources
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
MKT2013 (CHAPTER 2)
Quiz
•
1st Grade
10 questions
Halal Agencies
Quiz
•
1st Grade
10 questions
Teamwork For Military Service
Quiz
•
1st - 12th Grade
10 questions
portfolio assessment
Quiz
•
1st - 5th Grade
10 questions
It's all about Santa Laurensia
Quiz
•
3rd Grade
10 questions
Fixed Voice & VAS
Quiz
•
1st Grade
10 questions
Customer Requests
Quiz
•
1st Grade
10 questions
Supplementary Non-Technical Cases
Quiz
•
1st Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
10 questions
Probability Practice
Quiz
•
4th Grade
15 questions
Probability on Number LIne
Quiz
•
4th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
6 questions
Appropriate Chromebook Usage
Lesson
•
7th Grade
10 questions
Greek Bases tele and phon
Quiz
•
6th - 8th Grade
Discover more resources for Professional Development
10 questions
Probability Practice
Quiz
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
15 questions
Probability on Number LIne
Quiz
•
4th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade